Key Facts
- Governing section
- City Code § 29.5-3.06(a)(2)
- No-rise standard
- No increase in flood heights or velocities
- Minor dock exemption
- Must meet IDNR/OWR Statewide Permit No. 5
- Non-qualifying docks
- Need IDNR/OWR permit, FEMA approval, Council variance
- Enforcing official
- City Engineer, § 29.5-2.25
- Penalty
- Circuit Court fine, per-day violation, § 29.5-2.21
Summary
In a Champaign floodway, a boat dock is allowed without a separate city variance only if it qualifies as a "minor boat dock" meeting IDNR/OWR Statewide Permit No. 5. Any other dock needs an IDNR/OWR permit, FEMA sign-off on the flood map, and a City Council variance.
Within the floodway identified on the Flood Boundary and Floodway Map, and within all other floodplains where a floodway has not been delineated, the following standard shall apply: No development shall be allowed which, acting in combination with existing and anticipated development, will cause any increase in flood heights or velocities or create a threat to public health and safety.(a)The following specific development activities shall be considered as meeting this requirement:(1)Aerial utility crossings meeting the conditions of IDNR/OWR Statewide Permit No. 4;(2)Minor boat docks meeting the conditions of IDNR/OWR Statewide Permit No. 5;(3)Minor, nonobstructive activities meeting the conditions of IDNR/OWR Statewide Permit No. 6;
Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 80).
Full Breakdown
5, Article III governs development in the floodway, including docks. 06 sets the baseline test: no development may cause any increase in flood heights or velocities or threaten public health and safety. Minor boat docks are deemed to automatically satisfy that no-rise standard if they meet the conditions of Illinois Department of Natural Resources, Office of Water Resources (IDNR/OWR) Statewide Permit No. 5, the same treatment given aerial utility crossings (Permit No. 4) and minor, nonobstructive activities (Permit No. 6). A dock that does not fit the Statewide Permit No.
06(b) instead: it can only proceed if IDNR/OWR has issued a permit (or confirmed none is required), FEMA has approved any needed map revision, and the City Council has granted a variance. 24; the ZBA then makes a recommendation and the Council rules on it. 25.
Violations & Fines
The City Engineer serves a written notice of violation and can issue a stop-work order on an unpermitted or noncompliant dock under Section 29.5-2.20. A complaint may also be filed in Circuit Court; a conviction carries a fine up to the maximum set in Section 1-21 of the Municipal Code, with each day of continuing violation counted as a separate offense under Section 29.5-2.21. The City Attorney may additionally seek an injunction to halt or remove the unlawful structure.
Frequently Asked Questions
Do I need a city permit to build a boat dock in Champaign?
Who approves a floodway variance for a dock in Champaign?
What happens if I build a dock without required approval?
Sources & Official References
Other rules in Champaign
Compare Champaign to another location·View the Illinois environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.