Champaign, IL Environmental Rules: Flood Elevation Requirements (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Default data source
State Water Survey Floodplain Information Repository
Named waterways w/ FIS profiles
Boneyard Creek, Copper Slough, Phinney Branch
FIS date
July 16, 1980, as amended
A Zone method
USGS 1976 'Depth & Frequency of Floods' formula
Dispute process
applicant funds study, IDOT and City Engineer review
Penalty
$1-$500 per day, Sec. 9-224

Summary

Champaign measures floodplain protection against the base flood elevation set by the State Water Survey's Floodplain Information Repository, per Section 9-235 of the Municipal Code. For Boneyard Creek, Copper Slough, and the Phinney Branch, that elevation comes straight from the 1980 Flood Insurance Study's 100-year flood profiles; in other mapped 'A Zones,' the applicant's own engineer must calculate it.

(a)The protection standard used in this article is the base flood elevation established according to the best data available to the State Water Survey's Floodplain Information Repository. Whenever a party disagrees with the best available data, such party may finance the detailed engineering study needed to replace existing data. The detailed engineering study shall be submitted to the State Department of Transportation, Division of Waterways, and the City Engineer for review and approval.(b)The base flood elevation for the special flood hazard areas of the Boneyard Creek...and the Phinney Branch shall be as delineated on the 100-year flood profiles contained in the Flood Insurance Study, City of Champaign, dated July 16, 1980, as amended.(c)The base flood elevation for each of the remaining special flood hazard areas delineated as an "A Zone"...shall be the 100-year flood depth calculated by the applicant's engineer according to the formulas presented in "Depth & Frequency of Floods in Illinois," published by the U.S. Geological Survey, 1976, as amended.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 80).

Full Breakdown

Section 9-235 sets the technical method for pinning down the base flood elevation, the standard against which every floodplain development permit is measured. Subsection (a) makes the State Water Survey's Floodplain Information Repository the default source of the best available data; anyone who disputes that data has to personally finance a detailed engineering study, and that study must go to both the State Department of Transportation's Division of Waterways and the City Engineer for review and approval before it can replace the Repository figure. Subsection (b) locks in a specific data source for the City's named waterways, Boneyard Creek, Upper Boneyard Creek, the Third Street Boneyard Creek tributary, Copper Slough, the John Street Copper Slough tributary, and the Phinney Branch: their base flood elevation is whatever the 100-year flood profiles in the July 16, 1980 Flood Insurance Study for the City of Champaign show, as later amended.

S. Geological Survey's 1976 report 'Depth & Frequency of Floods in Illinois,' or an equivalent formula recommended by the State Water Survey. That calculated elevation is what the Building Safety Supervisor or City Engineer then compares against the site grade under Section 9-233 before a development permit can issue.

Violations & Fines

Developing below the base flood elevation established under Section 9-235, or building without the floodproofing that elevation requires elsewhere in the article, is a violation of the floodplain article and is punished under Section 9-224: not less than $1 nor more than $500 per offense, with every day the noncompliant structure stands counted as a new offense.

Frequently Asked Questions

How does Champaign determine the base flood elevation for my property?
It depends on location. For Boneyard Creek, Copper Slough, the Phinney Branch, and their tributaries, Section 9-235(b) uses the 100-year flood profiles from the City's 1980 Flood Insurance Study. For other mapped 'A Zones' without a set elevation, your engineer must calculate it using USGS formulas under Section 9-235(c).
Can I challenge Champaign's base flood elevation data?
Yes, but you pay for it. Section 9-235(a) lets a party who disagrees with the State Water Survey's data finance a detailed engineering study, which must then go to the Illinois Department of Transportation's Division of Waterways and the City Engineer for review and approval before it can replace the existing elevation.
What happens if I build below the base flood elevation?
That puts your development out of compliance with the floodplain article's elevation and floodproofing standards, and Section 9-224 sets the penalty at $1 to $500 per offense, with each day the violation continues counted separately, on top of jeopardizing the development permit itself.

Sources & Official References

Other rules in Champaign

All Champaign rules

Compare Champaign to another location·View the Illinois environmental rules overview

Get notified when Flood Elevation Requirements in Champaign, IL changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.