Key Facts

Permit required
Engineering permit + building permit
Engineering fee
4% of construction cost, $100 min
Side setback
5 feet from extended property line
Small waterway limit (<=50 ft wide)
Dock extends max 5 feet waterward
Large waterway dock limit
10% of width or 8 ft, whichever less
Variance-proof rules
§151.03(B) and (C) barred from variance

Summary

Building, repairing, or installing a dock, lift, or other mooring structure in Pompano Beach waterways requires an engineering permit from the City Engineer plus a building permit, with dock length and setback limits keyed to the width of the canal or waterway.

It shall be unlawful for any person to construct, repair, erect or install mooring structures, or any similar marine structures... in, over or upon the canals, waterways, rivers, or basins within the city without first obtaining an engineering permit from the City Engineer, as provided in this chapter and a building permit from the City Building Official as provided in Chapter 152.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: 2026 S-122: Supplement contains: Local legislation current through 2026-35, passed 7-29-26).

Full Breakdown

02 makes it unlawful to construct, repair, erect, or install mooring structures or similar marine infrastructure in the city's canals, waterways, rivers, or basins without first getting an engineering permit from the City Engineer and a building permit under Chapter 152. S. 813. Replacing structural elements like pilings, sub-stringers, stringers, or ledgers requires a permit, though replacing 25% or less of existing decking in a calendar year is exempt. The engineering fee is 4% of the construction cost, with a $100 minimum, and plans must be prepared by a Florida-licensed engineer with as-built drawings submitted before final city acceptance.

03 sets the physical limits: no mooring structure may sit within five feet of an extended side property line or extend into the navigational channel. In waterways 50 feet wide or less, fixed or floating docks cannot extend more than five feet waterward of the measurement reference line, while vessel davits, hoists, and lifts may extend to the navigational channel. In waterways over 50 feet wide, fixed docks and wharves may extend 10% of the waterway's width or eight feet, whichever is less; finger piers may extend 20% of the width or 20 feet, whichever is less, capped at four feet wide with at least 25 feet between piers.

Vessel lifts in a raised position may extend up to 28 feet. Nonconforming structures destroyed by fire, casualty, or force majeure must be rebuilt to current standards, but properly permitted structures needing repairs affecting 50% or less of combined structural elements may remain in their existing nonconforming configuration. 03(B) and (C) setback and channel limits cannot be varianced at all.

Violations & Fines

Constructing, repairing, or installing a mooring structure without the required engineering and building permits violates § 151.02 and is enforceable under the citywide general penalty, § 10.99: a fine up to $500, imprisonment up to 60 days, or both, with each day of violation a separate offense. Unsafe or hazardous structures may be ordered removed by the city at the owner's cost under § 151.03(D), after notice and a hearing.

Frequently Asked Questions

Do I need a permit to build a boat dock in Pompano Beach?
Yes. Section 151.02 requires an engineering permit from the City Engineer and a building permit under Chapter 152 before constructing, repairing, or installing any dock, lift, or mooring structure in city waterways, plus any required county, state, or federal approvals.
How far can a Pompano Beach dock extend into a narrow canal?
In a canal, river, basin, or waterway 50 feet wide or less, § 151.03(E) limits fixed or floating docks to no more than five feet waterward of the measurement reference line, though vessel davits and lifts may extend further to the navigational channel.
What does a dock permit cost in Pompano Beach?
The engineering permit fee is 4% of the proposed construction cost, with a minimum fee of $100, under § 151.02(D). Applicants also need a Chapter 152 building permit and plans prepared by a Florida-licensed engineer.

Sources & Official References

Other rules in Pompano Beach

All Pompano Beach rules

Florida rules heatmap·Compare Pompano Beach to another location·View the Florida environmental rules overview

Get notified when Boat Dock Permits in Pompano Beach, FL changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Boat Dock Permits in Nearby Cities

How other cities in Broward County handle boat dock permits.

Pembroke Pines, FL
Some Restrictions
Miramar, FL
Some Restrictions
Hollywood, FL
Significant Restrictions
Fort Lauderdale, FL
Significant Restrictions