Abilene, TX Environmental Rules: Erosion Control (2026)
Key Facts
- Required plan
- Stormwater pollution prevention plan (SWP3)
- State permits covered
- TPDES TXR150000 (construction), TXR050000 (industrial)
- Notice filed with
- Stormwater Utilities Division, 555 Walnut St.
- Debris cleanup window
- Up to 72 hours after City notice
- SWP3 correction window
- 30 days to fix deficiencies
- Enforcing office
- Stormwater Utility Division Administrator
Summary
Construction sites in Abilene that need a state TPDES stormwater permit must file a stormwater pollution prevention plan and notify the City's Stormwater Utility Division before breaking ground. Tracking sediment, concrete, or debris into the municipal storm drain system is a separate violation, enforced under Code of Ordinances §§ 32-241 and 32-190(c).
State of Texas regulations require that subject facilities apply for and obtain general permits for industrial facilities (TPDES TXR050000) and construction sites (TXR150000) that have been determined to contribute or have the potential to contribute substantial pollutant loads to the municipal stormwater drainage system or waters of the state. The general permits require that the permitee develop, implement, and maintain a stormwater pollution prevention plan (SWP3) and submit a notice of intent notifying the TCEQ and the municipal stormwater drainage system operator (City of Abilene)... The introduction of sediment, concrete, asphalt, or any other construction debris into the municipal stormwater drainage system from a construction activity is a violation of this article and will be subject to enforcement activities.
Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 14).
Full Breakdown
Division 5 of Chapter 32 requires facility owners and operators to comply with the erosion and sediment controls tied to the two state general permits that cover most Abilene construction sites: TPDES general permit TXR150000 for construction activity and TXR050000 for industrial facilities. Section 32-241(b) states these permits require the permittee to "develop, implement, and maintain a stormwater pollution prevention plan (SWP3)" and to submit a notice of intent to both TCEQ and the City as MS4 operator; smaller sites that fall under the permit's notice-only threshold instead file a construction site notice under § 32-291, delivered in person or mailed to the Stormwater Utilities Division at 555 Walnut Street, Suite 210.
The City's MS4 permit obligates it to inspect construction sites and enforce control-measure requirements, so § 32-242 gives the Administrator a right of entry during normal working hours to check a site's SWP3 against actual conditions, look for illicit connections, and collect samples. Section 32-243 lets the Administrator order a written correction of SWP3 deficiencies within 30 days. Separately, § 32-190(c) makes it a standalone violation to let sediment, concrete, asphalt, or other construction debris reach the municipal storm drain system, and gives an operator up to 72 hours to remove it once notified.
Section 32-314 extends the same control duty to stockpiles, soil piles, and material heaps on any site in the City limits that could wash into the storm system, and lets the Administrator require specific control measures to keep that from happening.
Violations & Fines
Operating without the required NPDES/TPDES permit, or without an SWP3 that matches site conditions, is an offense under § 32-190(a) and § 32-245(b). Letting sediment or debris reach the storm system under § 32-190(c) triggers a mandatory cleanup window of up to 72 hours. Ongoing violations under § 32-341 are misdemeanors fined per Code of Ordinances § 1-9, with each day of noncompliance charged separately, on top of any state TCEQ enforcement.
Frequently Asked Questions
Does a construction site in Abilene need its own stormwater plan?
What happens if concrete or dirt washes into the storm drain from my site?
Can the City inspect my construction site?
Sources & Official References
Other rules in Abilene
Texas rules heatmap·Compare Abilene to another location·View the Texas environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.