Key Facts

Permit issuer
City Engineer
Application review time
10 business days
Permit duration
180 days, extendable
Inspection trigger
Within 24 hrs of 0.5" rain
First-offense fine
$10 to $500 per day

Summary

Burlington requires a City Engineer-issued permit and an approved erosion and sediment control plan before any land-disturbing construction activity begins. Chapter 148 sets design standards, inspection schedules, and a forfeiture of $10 to $500 per day for violations of its erosion-control requirements.

A. Permit required. No responsible party may commence a land-disturbing construction activity subject to this chapter without receiving prior approval of an erosion and sediment control plan for the site and a permit from the City Engineer. ... B. Permit application and fees. At least one responsible party desiring to undertake a land-disturbing construction activity subject to this chapter shall submit an application for a permit and an erosion and sediment control plan that meets the requirements of § 148-10 and shall pay an application fee as determined on the permit application form to the City of Burlington Building Inspector. By submitting an application, the applicant is authorizing the City Engineer to enter the site to obtain information required for the review of the erosion and sediment control plan. Fees will double for any land disturbance activities requiring a permit beginning prior to receiving a permit.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: rev 4997580; v29 updated 2026-07-07; through 07-07-2026).

Full Breakdown

234, Wis. , bars any responsible party from starting land-disturbing construction activity without first getting the City Engineer's approval of an erosion and sediment control plan and a permit, per § 148-9A. Applicants submit the plan and application, along with a fee that doubles if disturbance work starts before the permit issues, to the City of Burlington Building Inspector. The City Engineer has 10 business days after a complete application to approve or disapprove it, stating reasons in writing for any disapproval, and failing to respond within that window counts as automatic approval.

The City Engineer can require a surety bond or irrevocable letter of credit to guarantee the plan gets carried out. Permit holders must notify the City Engineer within 48 hours of starting work and within 14 days of finishing best management practices (BMPs), inspect BMPs within 24 hours of any half-inch rain event during active construction and at least weekly, and log each inspection's date, inspector, and site conditions. Permits last 180 days, or as long as the underlying building permit, whichever is longer, and the City Engineer can extend that period.

The chapter applies to sites with land-disturbing activity that are part of a common plan of development, and the City Engineer can bring smaller sites under the chapter if their runoff threatens drainage capacity or public safety. State agencies, agricultural and silviculture operations, and most transportation facilities are excluded.

Violations & Fines

The City Engineer may post a stop-work order for activity without a permit, plan noncompliance, or violated permit conditions, and can revoke the permit if work does not stop. Under § 148-13F, any violation of Chapter 148 carries a forfeiture of not less than $10 nor more than $500 plus prosecution costs, with each day of continued violation a separate offense; the City may also seek an injunction or a cease-and-desist order.

Frequently Asked Questions

Do I need a permit to grade or clear land in Burlington?
Yes, if the activity qualifies as land-disturbing construction under Chapter 148. Section 148-9A requires an approved erosion and sediment control plan and a City Engineer permit before work starts, submitted with a fee to the Building Inspector.
What happens if construction starts before my erosion permit is approved?
The application fee doubles for any land disturbance that begins before the permit is issued, and the City Engineer can post a stop-work order and later revoke the permit if the violation continues.
How often must erosion controls be inspected during construction?
The responsible party must inspect best management practices within 24 hours after any rainfall of half an inch or more during active construction, and at least once every week, logging the date, inspector, and site conditions.

Sources & Official References

Other rules in Burlington

All Burlington rules

Compare Burlington to another location·View the Wisconsin environmental rules overview

Get notified when Erosion Control in Burlington, WI changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.