Key Facts

Permit trigger
2,000 sq ft or more of ground disturbance
Baseline standard
Minimize erosion using best management practices
Enforcer
City Manager, erosion/sediment control program
Penalty
$100-$5,000/offense; each day a separate offense
Appeal fee
$250, filed within 7 days plus 3 mailing
Plan required
Approved control plan before ground disturbance

Summary

The City of Corvallis requires an Erosion Prevention and Sediment Control (EPSC) permit before any ground-disturbing construction activity affecting 2,000 square feet or more, cumulatively, under Section 9.03.090 of the Corvallis Municipal Code. Erosion and sediment release must be minimized to the greatest extent practicable using best management practices, and violators face a fine of $100 to $5,000 per offense, with each day a separate violation.

Erosion and sediment release shall be minimized to the greatest extent practicable utilizing best management practices and the standards in the Erosion Prevention and Sediment Control Manual. ... An erosion prevention and sediment control (EPSC) permit is required before commencing ground disturbing activity affecting 2,000 square feet or greater, cumulatively, throughout the duration of the development. ... 4)Penalties. Any person violating any of the provisions herein for which a penalty has not been otherwise provided, shall upon court conviction thereof, be punished by a fine of at least $100.00 but not more than $5,000.00 per offense. Each day that a violation exists is a separate offense.

Full Breakdown

Chapter 9.03, the City of Corvallis Erosion Prevention and Sediment Control Standards, applies to all ground-disturbing activity in the city, whether or not a permit is required, unless specifically exempted under Section 9.03.030. Section 9.03.080 sets the baseline standard: erosion and sediment release must be minimized to the greatest extent practicable using best management practices and the City's Erosion Prevention & Sediment Control Manual, with the City Manager judging compliance against visible and measurable erosion criteria. Section 9.03.090 requires an EPSC permit before any ground-disturbing activity that affects 2,000 square feet or more cumulatively over the life of a development, and Section 9.03.100 requires an approved Erosion Prevention & Sediment Control Plan before that activity, or installation of any control measures, can begin; grading, public improvement and building permits are withheld until the plan is implemented.

If erosion is already occurring, the responsible party must immediately install interim controls and submit a long-term revision for approval. The City Manager enforces the Standards, can inspect with consent or an administrative warrant, issue stop-work orders halting all work except correction of the violation, and pursue summary abatement of an immediate hazard under Section 9.03.140, billing the property owner for the City's costs. Section 9.03.110(4) sets the default criminal penalty at not less than $100 nor more than $5,000 per offense, with each day of violation a separate offense.

Appeals of technical determinations go to the Hearings Officer, and procedural appeals to the City Council, within 7 days plus 3 for mailing, on a $250 filing fee.

Violations & Fines

Disturbing 2,000 square feet or more of ground without an approved EPSC permit and plan, or letting erosion or sediment leave a site without corrective best management practices, violates Chapter 9.03. The City Manager can issue a stop-work order and, on conviction, a court fine of at least $100 and up to $5,000 per offense, with each day of continuing violation a separate offense.

Frequently Asked Questions

When does a Corvallis construction project need an erosion control permit?
Section 9.03.090 requires an Erosion Prevention and Sediment Control (EPSC) permit before any ground-disturbing activity that affects 2,000 square feet or more, counted cumulatively over the whole project. An approved control plan under Section 9.03.100 must be in place, and grading, building or public improvement permits won't issue until it is implemented.
What happens if a Corvallis site is eroding without a permit?
The City Manager can issue a written stop-work order under Section 9.03.110 halting all work except correcting the problem, require immediate interim controls, and pursue summary abatement of an imminent hazard under Section 9.03.140. A court conviction carries a fine of $100 to $5,000 per offense, with each day counted separately.
Who enforces Corvallis's erosion and sediment control standards?
The City Manager administers and enforces the Erosion Prevention and Sediment Control Standards in Chapter 9.03, including plan review, permit issuance, inspections and stop-work orders. Appeals of technical or scientific determinations go to a Hearings Officer, while procedural appeals go to the City Council, within 7 days plus 3 for mailing.

Sources & Official References

Other rules in Corvallis

All Corvallis rules

Compare Corvallis to another location·View the Oregon environmental rules overview

Get notified when Erosion Control in Corvallis, OR changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.