Dade City, FL Environmental Rules: Erosion Control (2026)
Key Facts
- Governing section
- Code § 42-252(a)
- Adopted
- Ord. No. 99-0743, October 26, 1999
- Core duty
- Retain sediment onsite, meet NPDES/state permit
- Notice required
- Before discharging from industrial/construction sites
- Enforcement
- City manager, written notice + corrective plan
- Serious risk
- Cease-and-desist order by registered mail
Summary
Dade City, Pasco County, Florida, requires construction sites to control stormwater so sediment stays onsite and state water quality standards are not violated, under Code § 42-252(a), tying compliance to whatever NPDES or state stormwater permit already governs the site.
(a)Stormwater from construction sites shall be controlled in such a way as to retain sediment onsite and prevent violations of state water quality standards, or NPDES permits. All erosion, pollution, and sediment controls required pursuant to the pollution prevention plan of a NPDES stormwater permit for construction or required pursuant to a state stormwater permit issued by either the state department of environmental regulation or the Southwest Florida Water Management District shall be properly implemented, maintained and operated.
Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 18 | Land Development Regulations: Supplement 1).
Full Breakdown
Section 42-252(a) of the Dade City Code of Ordinances, part of the city's stormwater management article adopted by Ord. No. 99-0743 on October 26, 1999, requires that stormwater from construction sites be controlled so as to retain sediment onsite and prevent violations of state water quality standards or NPDES permits. Rather than setting its own separate numeric erosion table, the section incorporates whatever erosion, pollution and sediment controls are already required under the pollution prevention plan of a site's NPDES construction stormwater permit, or under a state stormwater permit issued by the state department of environmental regulation or the Southwest Florida Water Management District, and requires that those controls be properly implemented, maintained and operated throughout construction.
Section 42-252(c) separately requires owners or operators of industrial facilities or construction sites discharging stormwater to the city's municipal separate storm sewer system to give the city written notice before discharging. Administration runs through the city manager under § 42-225: a violation triggers a written notification requiring the responsible party to propose corrective measures and a completion schedule, subject to the city manager's approval, and the city manager can issue a cease-and-desist order by registered mail if the situation could seriously affect public health, safety or the environment, or if irreversible harm could result.
Prosecution follows the general penalty in § 1-7, and a violator responsible for a discharge that harms a receiving water is also liable for sampling, analytical costs, any state or federal fines, and the cost of restoring the water.
Violations & Fines
A construction site found to be violating § 42-252(a) receives written notification from the city manager under § 42-225 requiring a corrective action plan and schedule. Serious risk to health, safety or the environment can bring an immediate cease-and-desist order by registered mail. Violators face prosecution under § 1-7, plus liability for sampling costs, any state or federal fines, and full restoration costs for any receiving water harmed.
Frequently Asked Questions
Does Dade City have its own erosion control numbers for construction sites?
Who enforces stormwater rules on a Dade City construction site?
Do I need to notify the city before a construction site discharges stormwater?
What can it cost me if my construction site's runoff damages a waterway?
Sources & Official References
Other rules in Dade City
Florida rules heatmap·Compare Dade City to another location·View the Florida environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.