Key Facts

Trigger slope
Steeper than 4:1 (horizontal to vertical)
Winter seed rate
90 lbs/acre bermuda + 30 lbs/acre rye
Summer seed rate
60 lbs/acre bermuda + 50 lbs/acre millet
Fertilizer rate
1,000 lbs/acre of 10-10-10
Extra measures trigger
Longitudinal slope over 5 percent

Summary

Developers in unincorporated Darlington County must stabilize graded slopes steeper than 4:1 with hydroseeding, sod, or hand-seeding and mulching under the county's drainage standards, with specific seed and fertilizer rates set by season.

These county ordinances apply to unincorporated areas of Darlington County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

(H)Erosion control. Whenever graded earthen slopes are steeper than 4:1 (4 horizontal to 1 vertical), and in other areas where erosion is deemed potentially damaging by the county, grass seed shall be planted by hydroseeding, placing sod mats or seeding by hand and mulching.(1)Hydroseeded grassing shall be performed using Method C (wood cellulose fiber tackifer) in accordance with S.C.D.H.P.T. Standard Specifications section 810.18. Grass seeded from August 15 - March 1 to be 90 lbs. per acre common bermuda (unhulled) and 30 lbs. per acre annual rye grass. Grass seeded from March 1 - August 15 is to be 60 lbs. per acre common bermuda (hulled) and 50 lbs. per acre brown top millet. Rate of 10-10-10 fertilizer application to be at 1000 lbs. per acre and agricultural lime shall be applied at a rate of 2500 lbs. per acre.( ... 3)Additional erosion control measures may be necessary where excessive siltation of drainage works occurs and where longitudinal slopes exceed five percent. Special drainage provisions must be approved by the county and may include silt fences, riprap, piping, silt dams, etc.

Full Breakdown

Section 5.6(H) of the Development Standards Ordinance, Appendix A, requires grass seed to be established by hydroseeding, sod mats, or hand seeding with mulching whenever graded earthen slopes exceed 4:1 (four horizontal to one vertical), or wherever the county determines erosion risk is significant. The hydroseeding method must follow SCDOT Standard Specifications Section 810.18 using Method C wood cellulose fiber tackifier. Seasonal seed rates are set precisely: seeding done August 15 through March 1 must use 90 pounds per acre of unhulled common bermuda plus 30 pounds per acre of annual rye grass, while seeding from March 1 through August 15 must use 60 pounds per acre of hulled common bermuda plus 50 pounds per acre of brown top millet.

Fertilizer must be applied at 1,000 pounds per acre of 10-10-10 and agricultural lime at 2,500 pounds per acre. The resulting stand of grass must meet SCDOT Standard Specifications Section 810.13. Where longitudinal slopes exceed five percent or drainage works show excessive siltation, the county can require additional measures such as silt fences, riprap, piping, or silt dams, all subject to county approval before installation. This erosion control duty sits within the broader drainage standards of Section 5.6, which also makes the developer responsible for any damage to drainage facilities during construction and for two years of storm drain maintenance liability after county acceptance, or until 80 percent of the lots have sold.

Violations & Fines

Failure to establish the required grass stand or install approved erosion control measures blocks final acceptance inspection of the road or drainage system under Section 5.2(C)(1)(g); the county can require an escrow deposit sufficient to cover re-grassing costs if a stand of grass has not taken hold within one year, with the funds used by the county to complete the work if the developer fails to do so.

Frequently Asked Questions

When does Darlington County require erosion control on a construction site?
Section 5.6(H) of the Development Standards Ordinance requires grass stabilization by hydroseeding, sod, or hand seeding and mulching whenever graded earthen slopes are steeper than 4:1, or in any other area the county deems potentially damaging from erosion.
What seed mix does Darlington County require for erosion control?
From August 15 to March 1 the code requires 90 pounds per acre of unhulled common bermuda and 30 pounds per acre of annual rye grass; from March 1 to August 15 it requires 60 pounds per acre of hulled common bermuda and 50 pounds per acre of brown top millet, plus 1,000 pounds per acre of 10-10-10 fertilizer.
What happens if erosion control grass fails to establish?
Under the county's road acceptance procedure, the developer may need to post an escrow amount adequate to cover re-grassing; if grass has not taken hold within one year, the county keeps the escrow and uses it to establish the required stand itself.

Sources & Official References

Other rules in Darlington County

All Darlington County rules

Compare Darlington County to another location·View the South Carolina environmental rules overview

Get notified when Erosion Control in Darlington County, SC changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.