Key Facts

Governing article
Appendix A, Article Seventeen
SWPPP trigger
1+ acre land disturbance
Application fee to DHEC
$125 plus $100/acre, max $2,000
Inspection frequency
Every 7 or 14 days
Noncompliance fine
$500 per day
Enforcing office
Director of Planning

Summary

Unincorporated Darlington County bans illicit discharges and illicit connections to its MS4 storm drain system under Appendix A, Article Seventeen. Any land disturbance of one acre or more needs a county-approved SWPPP before grading starts, and the Planning Department's director of planning enforces the article with inspections, corrective orders and misdemeanor fines up to $500 per day.

These county ordinances apply to unincorporated areas of Darlington County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

A.Darlington County prohibits illicit discharges and illicit connections, as defined in Section 17.3.A. of this article. ... C.A person is considered to be in violation of these regulations if the person connects a line conveying sewage to the MS4, or allows such a connection to continue. ... 7.Failure to comply with order. If the user fails to comply with an order to take corrective action from which no appeal has been made, or fails to comply with an order of the governing body following an appeal, he shall be subject to a fine of $500.00. If a fine is levied, each day where no corrective action has been taken may be considered a separate offense with a separate fine. If no corrective action is taken within five days, it shall constitute a misdemeanor and the violator may be charged.

Full Breakdown

Darlington County created its Municipal Separate Storm Sewer System (MS4) Area Stormwater Management Protection Overlay District under Appendix A, Article Seventeen, mapped in Plat Book 204 at page 45 and administered by the county's Planning Department. Section 17.4.3 prohibits illicit discharges and illicit connections to the storm drain system, including any past connection that conveys sewage into the MS4, and Section 17.4.4 gives the county the right to enter and inspect any facility subject to an NPDES stormwater permit as often as necessary, with a search warrant available if access is refused.

Section 17.5.1 requires an approved stormwater pollution prevention plan (SWPPP) and a certificate of approval from the director of planning before any land disturbance of one acre or more, plus coverage under SCDHEC's General Permit SCR100000; single-family homes disturbing less than an acre and outside a subdivision are exempt. The application fee is $125 forwarded to DHEC with the notice of intent plus a $100-per-acre county review fee, capped at $2,000, for a maximum of $2,125 under Section 17.5.4. Inspections during construction must occur at least every seven days, or every 14 days plus within 24 hours of a 0.5-inch storm, per Section 17.5.6.

Under Section 17.4.9, a violator gets written notice, a hearing before the director of planning within ten days, and an order to correct within 60 days (less if there is imminent danger); an unappealed or unheeded order triggers a $500 fine, with each day of continued noncompliance a separate offense, and failure to correct within five days becomes a misdemeanor. The county may also suspend MS4 access without notice for an imminent threat.

Violations & Fines

Failure to obtain SWPPP approval before disturbing an acre or more, or making an illicit connection to the MS4, draws a written notice and corrective order from the director of planning. Ignoring an unappealed order brings a $500 fine, with each day of continued violation a separate offense; failing to correct within five days is a misdemeanor prosecuted in county court, and the county may also suspend or terminate MS4 access.

Frequently Asked Questions

Does every construction project in Darlington County need a stormwater permit?
Only if it disturbs one acre or more, or is part of a larger common plan of development that will reach one acre, per Section 17.5.1. Single-family homes disturbing under an acre and not part of a subdivision are exempt under Section 17.5.2.
What happens if I connect a sewage line to the county storm drain?
Section 17.4.3.C makes that a violation regardless of when the connection was made. The director of planning issues a written notice, and an unappealed order to correct can lead to a $500 fine with each day of noncompliance counted separately.
How often are active construction sites inspected?
Section 17.5.6 requires the owner or operator to inspect at least every seven calendar days, or every 14 days plus within 24 hours after a storm event of 0.5 inches or more, with records kept on-site alongside the SWPPP.
Who administers the MS4 program in Darlington County?
The Darlington County Planning Department's director of planning administers Article Seventeen, reviewing SWPPPs, conducting inspections and issuing enforcement orders, with the county council hearing appeals of final orders.

Sources & Official References

Other rules in Darlington County

All Darlington County rules

Compare Darlington County to another location·View the South Carolina environmental rules overview

Get notified when Stormwater Management in Darlington County, SC changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.