Davis County, UT Environmental Rules: Erosion Control (2026)
Key Facts
- Permit trigger
- disturbing 1 acre or more of ground
- Required plan
- Storm Water Pollution Prevention Plan (SWPPP)
- Also required
- separate state Division of Water Quality permit
- Enforcing agency
- Davis County Public Works Department
- Review timeline
- 30 days to approve, condition or deny
- Street rule
- no tracking mud or stockpiling fill in gutters
Summary
Anyone disturbing one acre or more of ground in unincorporated Davis County must obtain a General Construction County Storm Water Permit from the Public Works Department and get a Storm Water Pollution Prevention Plan approved before breaking ground. The county also requires a companion state permit, a review fee scaled to acreage, and a performance bond, and separately bans tracking mud onto public streets.
Any person or business responsible for disturbing one acre or more of ground shall obtain a General Construction County Storm Water Permit from the Public Works Department. No person shall be granted a General Construction County Storm Water Permit for land-disturbing activity that would require the uncovering of 1 acre or more without the approval of a Storm Water Pollution Prevention Plan by the Public Works Department... The applicant must also obtain a General Construction Storm Water Permit from the Department of Environmental Quality, Division of Water Quality... It is unlawful for any person to: Track mud or sediment onto public streets by construction or delivery vehicles. Provisions shall be made at all construction sites to either clean the streets or clean the vehicles or both before vehicles leave the site.
Full Breakdown
080 requires any person or business disturbing one acre or more to get a General Construction County Storm Water Permit from the Public Works Department, and bars the Department from granting one for a site that size without first approving a Storm Water Pollution Prevention Plan (SWPPP). The applicant must also separately obtain a General Construction Storm Water Permit from the Utah Division of Water Quality, post a faithful performance bond or letter of credit sized to cover improvement, maintenance and inspection costs, and pay a review fee scaled to the acreage disturbed, due before any building permit issues.
Emergency work and existing nursery or agricultural operations are exempt from the acre-or-more permit. The Department can waive the SWPPP requirement in whole or part if the project will not impair the ordinance's goals, if an alternative plan is already approved, or if site conditions make the standard plan infeasible, but only if the waiver will not degrade downstream culverts, habitat, streambanks or flood capacity. 100 layers on design criteria: the plan must address topography, drainage area, water table depth and slope, and every storm water facility needs a recorded maintenance agreement and easement, enforceable against the responsible party.
060 bans tracking mud onto public streets, washing out concrete trucks outside designated areas, and stockpiling fill, sand, gravel or mulch in the street or gutter without Public Works pre-approval.
Violations & Fines
Violating the storm water ordinance or a permit's terms lets Public Works suspend or revoke the site's storm water permit and issue a stop-work order, on top of requiring monitoring, cleanup and restoration of any affected property. Every violation is a misdemeanor, and each day a violation continues counts as a separate offense under Section 14.24.110.
Frequently Asked Questions
Do I need a permit to grade more than an acre in unincorporated Davis County?
Can the county waive my erosion-control plan?
What happens if my contractor tracks mud onto the street?
Sources & Official References
Other rules in Davis County