Doña Ana County, NM Environmental Rules: Erosion Control (2026)
Key Facts
- Governing section
- § 350-605D, Erosion control plan
- Grading limit
- Building pad + pond + driveway + 5 ft
- Existing-property notice
- 30 days to submit an ECP
- Plan cure period
- 10 working days to fix insufficiency
- Plan preparer
- NM-licensed professional engineer required
- Reviewing office
- Engineering and Site Development (ESD)
Summary
Any grading, construction, demolition or development that needs a county permit must have an approved erosion control plan (ECP) in place first, under § 350-605D of the Doña Ana County Code. Grading is capped to the building pad, pond, driveway and five extra feet around them unless the applicant justifies more, and the plan can be folded into construction drawings.
Erosion control plan (ECP). Any grading, construction, demolition, or development requiring a permit or other form of approval under any County ordinance shall have an approved ECP in place prior to receiving a permit. The ECP may be separate documents, or incorporated as part of required construction plans. ... New development. Any development that requires a permit under any County ordinance shall require an ECP be submitted consistent with this section. Grading for all construction, including single-family dwelling units, shall be limited to the building pad, pond, driveway, and an additional five feet in all directions from these areas, unless a need for additional area is demonstrated.
Full Breakdown
Section 350-605D of the Unified Development Code requires an approved erosion control plan before the county will issue a grading, construction, demolition or development permit; the ECP can stand alone or be built into the required construction plans. For new development, grading tied to single-family and other construction is limited to the building pad, any pond, the driveway, and an additional five feet in every direction beyond those areas, unless the applicant demonstrates a need for more disturbed ground. The rule also reaches existing, already-developed properties: if a code enforcement officer or other authorized county agent determines a property poses a significant erosion-driven health threat, particularly near schools or vulnerable populations, the owner has 30 days from written notice to submit an ECP to the Engineering and Site Development (ESD) office, which decides whether the plan is sufficient; an owner told a plan is insufficient gets 10 working days to fix it.
The ECP itself must be developed by a New Mexico-licensed professional engineer and include a site plan showing total disturbed acreage, all fugitive-dust sources, and best management practices such as watering, dust suppressants, temporary wind fences, native reseeding, and phased grading limited to street and utility work. Exempt activities include routine Right to Farm Act agriculture, government emergency response, essential utility service outages, and unpaved-lot uses generating fewer than 20 vehicle trips a day for under three days. A grading permit obtained under this article that is abandoned before completion, meaning no significant work continues on site, is itself a violation of § 350-605A.
Violations & Fines
Failing to continue significant work on a permitted grading site is deemed abandonment and a violation of § 350-605A. A property owner given written notice of an existing erosion hazard who does not submit an ECP within 30 days, or who fails to correct an insufficient plan within the 10 working days allowed, remains out of compliance and subject to county enforcement action under the article.
Frequently Asked Questions
Do I need an erosion control plan for a single-family home in unincorporated Doña Ana County?
What if the county says my existing lot is eroding badly?
Is farmland exempt from the erosion control plan requirement?
Sources & Official References
Other rules in Doña Ana County
Compare Doña Ana County to another location·View the New Mexico environmental rules overview