Edison, NJ Environmental Rules: Erosion Control (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Permit trigger
Soil/vegetation disturbance over 5,000 sq ft
Standalone review body
Environmental Commission (15-day recommendation)
Fee without building permit
$50 for first acre, then $10/acre
Appeal window
10 days to Township Council
Permit term
6 months, one extension available
State coordination
Freehold Soil Conservation District

Summary

Edison Township requires a land disturbance permit before clearing over 5,000 square feet of vegetative cover or grading, bulldozing or filling soil anywhere in the Township, under Code Section 32-3.2. Single-family lots, farms and home gardens get a narrow exemption that disappears near steep slopes or streams, and permits route through the Freehold Soil Conservation District or the Environmental Commission.

Except as otherwise provided herein, no land in the Township in excess of five thousand (5,000) square feet shall be cleared and left barren of vegetative protection, whether that protection consists of trees as defined herein, saplings, shrubs or grasses; and no such area shall otherwise be disturbed in the soil by bulldozing, earth moving, filling, leveling or other grading, laying of pipe or cable, or otherwise by any person, association, corporation, or public agency without a land disturbance permit first having been obtained as provided in this section.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: rev 4904708; v19 updated 2026-03-25; through 03-25-2026).

Full Breakdown

Section 32-3.1 states the purpose bluntly: preserve trees and woodlands from unjustifiable destruction, preserve soil from erosion and sedimentation, and protect the use and transfer of topsoil for the well-being of Edison residents and downstream neighbors. Section 32-3.2 backs that up with the permit trigger: clearing that leaves more than 5,000 square feet barren of vegetative cover, or any bulldozing, earth moving, filling, leveling, grading, or pipe and cable laying that disturbs soil, requires a land disturbance permit first.

Section 32-3.3 exempts home gardening, farming approved by the Freehold Soil Conservation District, and a single-family dwelling with accessory structures disturbing under 5,000 square feet, but that home exemption disappears if the lot sits on a slope of 10% or more or within 50 feet of a stream or flood hazard area. The appointed officer, the Township Engineer, can void any exemption where the activity would likely cause erosion or sedimentation and demand corrective plans. Applications tied to a subdivision, site plan or building permit are reviewed together with input from the Freehold Soil Conservation District where state law requires it; standalone applications go to the Environmental Commission, which has 15 days to make a non-binding recommendation, and standalone permits expire after six months unless extended. Section 32-3.9 lets the Township require a performance guarantee, and Section 32-3.10 authorizes a stop-operations order if work strays from the certified plan, plus withholding of certificates of occupancy until erosion control compliance is confirmed. Fees under Section 32-3.11 run $10 with a building permit outside Soil Conservation District certification, or $50 for the first acre, $10 per acre from one to 20 acres, and $5 per acre beyond that, when no building permit, subdivision or site plan is involved.

Violations & Fines

Violators face the general penalty set in Chapter 1, Section 1-5, under Section 32-3.13, with each day a violation continues counted as a separate offense. The Appointed Officer can also issue a stop-operations order under Section 32-3.10(b) when work departs from the certified plan, and no certificate of occupancy issues until a compliance report on permanent erosion controls reaches the municipal agent and the Soil Conservation District. Projects under District jurisdiction face separate District penalties too.

Frequently Asked Questions

Do I need a permit to clear my yard for landscaping in Edison?
Only if the disturbed area exceeds 5,000 square feet, or if your lot sits on a slope of 10% or more or within 50 feet of a stream or flood hazard area under Section 32-3.3, which strips the single-family home exemption even for smaller projects.
How much does an Edison land disturbance permit cost?
Under Section 32-3.11, an application without a building permit, subdivision or site plan costs $50 for the first acre, $10 per acre from one to 20 acres, and $5 per acre beyond twenty. A building-permit application not certified by the Soil Conservation District costs $10.
What happens if I disturb soil without a permit?
The Township can prosecute under Section 32-3.13, which applies Chapter 1's general penalty and treats each day of the violation as a separate offense. The Appointed Officer can also halt work immediately with a stop-operations order under Section 32-3.10(b).
Can I appeal a denied land disturbance permit application?
Yes. Section 32-3.12 gives applicants 10 days from written notice of denial to file an appeal with the Township Clerk, and the Township Council holds a public hearing before affirming, modifying or reversing the Appointed Officer's decision.

Sources & Official References

Other rules in Edison

All Edison rules

Compare Edison to another location·View the New Jersey environmental rules overview

Get notified when Erosion Control in Edison, NJ changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.