Irvine, CA Environmental Rules: Erosion Control (2026)
Key Facts
- Governing section
- Irvine Municipal Code § 5-10-137
- Plan required before
- Grading permit issuance
- Standby BMP deployment window
- 48 hrs of 50% storm forecast
- Desilting basin compaction
- 90% relative compaction minimum
- Non-compliance remedy
- Permit revocation, § 5-10-138(E)
Summary
Before Irvine issues a grading permit, developers must have an approved erosion and sediment control plan on file, install BMPs like desilting basins and check dams, deploy standby protection within 48 hours of a predicted storm, and retain a civil engineer to inspect the system through every rainy season.
Sec. 5-10-137. - Erosion and sediment control and water quality requirement systems. A.Prior to the issuance of grading permits, an erosion and sediment control plan for the proposed development shall be approved by the Chief Building Official. ... D.Paved streets, sidewalks and other improvements shall be maintained in a neat and clean condition free of loose soil, construction debris and trash. Street sweeping or other equally effective means shall be used on a regular basis to prevent wind, vehicle tracking or storm flows from carrying sediment and debris outside the project boundaries. Watering to clean streets is prohibited. ... K.Pursuant to the Statewide general construction permit, there shall be a "rain event" action plan and the ability to deploy standby erosion and sediment control BMPs as needed to completely protect the exposed portion of the site within 48 hours of a predicted storm event (a predicted storm event is defined as a forecasted, 50 percent chance of rain).
Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 20 | Zoning: Supplement 16).
Full Breakdown
Section 5-10-137 requires that, prior to grading permit issuance, an erosion and sediment control plan for the proposed development be approved by the Chief Building Official, who may order design or operational changes if weather-driven problems arise. Cut and fill slope faces must be protected against erosion, often through effective planting installed before final approval, and the code lists specific device categories: desilting basins, gravel bags, check dams, cribbing, and riprap, all fully implemented per the approved plan. Streets, sidewalks and site improvements must stay clean; street sweeping or an equally effective method is required, and watering to clean streets is expressly prohibited.
The owner must retain a civil engineer responsible for inspecting the erosion and sediment control system, approving installation of permanent and semi-permanent devices, and periodically reviewing field conditions throughout each rainy season. Desilting basins must meet current City design-capacity standards and, where built of compacted earth, reach 90 percent relative compaction, verified by a soil engineering report. Section 5-10-137(K) requires a "rain event" action plan under the statewide general construction permit, with standby BMPs deployable within 48 hours of a forecasted 50-percent chance of rain, and Section 5-10-137(L) requires effective planting on any slope over five feet high, with irrigation potentially required above 15 feet.
Section 5-10-138 adds post-storm duties: silt and debris must be removed from basins after every rainstorm, the system's performance evaluated and repaired, and if the Chief Building Official must perform emergency maintenance because the responsible party fails to, the grading permit can be revoked in writing and withheld until compliance and any penalty fee are satisfied. Grading commenced without a permit still triggers the erosion-control obligations under Section 5-10-138(F).
Violations & Fines
Failing to keep an approved, currently effective erosion and sediment control plan and BMPs deployed is a violation enforceable through Section 5-10-138: the Chief Building Official may perform emergency maintenance at the owner's expense (mobilization cost plus labor) and revoke the grading permit in writing, which then cannot be renewed until a compliant system is installed and any penalty fee paid. Watering to clean streets, a specifically banned practice under Section 5-10-137(D), is a separate code violation.
Frequently Asked Questions
Do I need an erosion control plan before I can grade in Irvine?
Can I hose down a construction site's streets to keep them clean in Irvine?
Who has to inspect erosion control devices during construction?
What happens if my erosion control system fails after a storm in Irvine?
Sources & Official References
Other rules in Irvine
California rules heatmap·Compare Irvine to another location·View the California environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.