Skip to main content

Issaquah, WA Environmental Rules: Erosion Control (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified November 2026

Key Facts

Governing section
IMC 16.26.050(C)(4), Temporary Erosion and Sediment Control
Wet season
October 1st through April 30th, with Director approval
Wet season plan deadline
September 1st, to the Development Services Department
Turbidity violation level
Over 100 NTUs at a monitoring point
Revegetation
Within seven days of completing grading or clearing
Daily penalty
$250.00 per day under a notice of violation and order
Small clearing exemption
Under 1,000 square feet in single-family zoning

Summary

In Issaquah, every land disturbing activity must provide a temporary erosion and sediment control (TESC) plan under IMC 16.26.050(C)(4). Devices go in before construction starts, wet season work from October 1st through April 30th needs the Director's specific approval, and turbidity above 100 NTUs at a monitoring point is a permit violation.

4. Temporary Erosion and Sediment Control. All land disturbing activities shall make provisions for temporary erosion and sediment control as follows: a. A temporary erosion and sedimentation control (TESC) plan and associated required documentation shall meet the following requirements: ... vii. ... Clearing and grading may be permitted to continue or to be initiated during the wet season (October 1st through April 30th) only if the Director grants specific approval per subsection (C)(4)(a)(ii) of this section. ... b. The TESC plan shall be designed to prevent, to the maximum extent practicable, the transport of sediment from the site to drainage facilities, surface waters, and adjacent properties. Turbidity in construction runoff at any monitoring point that exceeds 100 nephelometric turbidity units (NTUs) at any time up to the 10-year/24-hour storm event, as measured at the City’s rain gauge, is considered a violation of the permit, subject to stop work and enforcement as described in IMC 16.26.150 and 16.26.190 .

Full Breakdown

Section 16.26.050(C)(4) of the Issaquah Municipal Code applies to all land disturbing activities, and the Director applies it when deciding whether to issue a clearing, grading and stormwater permit. The TESC plan has to follow the best management practices in Minimum Requirement No. 2 of the adopted Stormwater Design Manual, which is the 2019 Washington State Department of Ecology Stormwater Management Manual for Western Washington as modified by the City of Issaquah 2022 Addendum.

The plan must show the construction sequence for all erosion control work, temporary and permanent, for the drier season and the wetter winter months. It must map the streams, wetlands, steep slopes and buffers, native growth protection easements, greenbelt and native vegetation areas that stay undisturbed, plus soil preservation areas and protection of existing trees and root systems. It must also provide a monitoring discharge point so turbidity in water leaving the site can be measured. Except on small sites as the Stormwater Design Manual defines them, the plan must be designed by, and carry the seal of, a civil engineer holding certified erosion and sediment control lead (CESCL) certification. Devices are installed before construction activities begin and maintained until all possibility for erosion has passed and permanent vegetation is established, as the Director determines.

The wet season runs October 1st through April 30th. A wet season TESC plan must reach the Development Services Department by September 1st for approval to start or continue clearing and grading. The Director weighs site conditions, the nature of the work, the contractor's previous performance, slope, soil type, hydrology and proximity to receiving waters. Where wet season clearing and grading is prohibited, building construction can continue as long as no additional clearing and grading is performed and effective erosion control stays in place. Disturbed areas not covered by permanent impervious surface must be revegetated within seven days of completing grading or clearing unless seasonal or weather conditions are unfavorable, and temporary measures stay in place until then. The City can require an updated TESC plan at any time during the permit term if the approved plan proves ineffective.

The same section caps artificially created slopes at three feet horizontal to one foot vertical (3H:1V), limits rockeries on uncontrolled fill to four feet, and requires engineered design for retaining walls over four feet. Clearing or grading less than 1,000 square feet where the existing zoning is single-family residential is exempt under IMC 16.26.040(B)(9).

Violations & Fines

Not installing TESC facilities before construction, not maintaining them, turbidity over 100 NTU in a rainfall event smaller than the 10-year/24-hour event (3.5 inches), missing a 30-day deadline for an updated TESC plan, or lacking a required CESCL on site each lets the Director suspend work or revoke the permit under IMC 16.26.150. Violations are civil violations and public nuisances under 16.26.190, and a notice of violation and order under Chapter 8.45 carries a cumulative $250.00 per day penalty.

Frequently Asked Questions

Can I clear and grade in Issaquah during the wet season?
Only with specific approval from the Director. A wet season TESC plan must be submitted to the Development Services Department by September 1st, and the Director reviews site conditions, slope, soil type, hydrology, proximity to receiving waters and the contractor's past performance. If approval is withheld, building construction can continue without additional clearing and grading.
What turbidity level counts as a violation?
Turbidity in construction runoff above 100 nephelometric turbidity units (NTUs) at any monitoring point, at any time up to the 10-year/24-hour storm event as measured at the City's rain gauge, is a permit violation under IMC 16.26.050(C)(4)(b). It is subject to stop work and enforcement under IMC 16.26.150 and 16.26.190.
Does a small single-family yard project need a TESC plan?
Clearing or grading less than 1,000 square feet where the existing zoning is single-family residential is exempt under IMC 16.26.040(B)(9). That exemption does not apply to activity within critical areas and their buffers under Chapter 18.802 IMC, so a lot beside a stream or wetland buffer loses it.
How tall can a rockery be on a cut or fill slope?
Rockeries on uncontrolled fill slopes are limited to four feet, measured from the bottom of the base rock. On cut slopes and reinforced or engineered fill slopes they can reach 12 feet with the Director's approval, and anything over four feet needs a geotechnical engineer's design and a wall drain.

Sources & Official References

Other rules in Issaquah

All Issaquah rules

Compare Issaquah to another location·View the Washington environmental rules overview

Get notified when Erosion Control in Issaquah, WA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Erosion Control in Nearby Cities

How other cities in King County handle erosion control.

Auburn, WA
Some Restrictions
Bellevue, WA
Some Restrictions
Federal Way, WA
Some Restrictions
Kent, WA
Some Restrictions
Kirkland, WA
Some Restrictions
Renton, WA
Some Restrictions
Seattle, WA
Some Restrictions