La Plata County, CO Environmental Rules: Erosion Control (2026)
Key Facts
- Plan scale
- Same scale as the site plan
- Required contents
- Measures, schedule, revegetation specs, disturbance extent, BMP drawings
- Completion deadline
- Before plat recording or land use permit
- Engineer's role
- Certifies improvements match approved plans
- Weed plan revegetation
- Within one calendar year of substantial completion
- Over 20 acres disturbed
- County can require long-term monitoring
Summary
In unincorporated La Plata County, Colorado, an applicant under Land Use Code § 70-9 must submit an erosion control plan showing construction measures, their schedule, revegetation specifications and the extent of disturbance. Improvements, revegetation and soil stabilization must be finished before plat recording or land use permit, with a professional engineer's certification.
E. Project Completion. ... 1. The applicant must complete improvements, revegetation measures, and soil stabilization prior to plat recording or land use permit. Additionally, a professional engineer shall submit a certification that the improvements have been constructed in accordance with the approved plans. ... ... C. Erosion control plan. ... The applicant shall submit an erosion control plan for the areas affected by the development. The erosion control plan shall be sufficiently detailed to evaluate soil erosion and the transport of sediments during construction. The erosion control plan shall be the same scale as the site plan and include: 1. Erosion control measures to be implemented during construction of the project; 2. Scheduling and implementation of these measures; 3. Revegetation specifications including seed mix, mulch, and application method; 4. Extent of proposed disturbance and revegetation; 5. Provide detailed drawings of best management practices or reference industry-standard details such as the CDOT M Standard Plans.
Full Breakdown
Section 70-9.IV.C requires the applicant to submit an erosion control plan for the areas affected by the development. It must be detailed enough to evaluate soil erosion and the transport of sediments during construction, and it is drawn at the same scale as the site plan. The plan lists the erosion control measures to be implemented during construction, the scheduling and implementation of those measures, revegetation specifications including seed mix, mulch and application method, the extent of proposed disturbance and revegetation, and detailed drawings of best management practices or references to industry-standard details such as the CDOT M Standard Plans.
The plan is one of four documents, alongside construction plans, grading plans and the drainage report, all prepared under the direction of and signed and sealed by a professional engineer unless the planning engineer waives that. The drainage report itself must cover implementation of the erosion control plan during construction activities. Preliminary versions go in with the project submittal and are revised and resubmitted until approved, and the final signed and sealed set is due before construction. Revisions after approval go to CDD for administrative approval before project completion.
The finish line is written into subsection III.E.1: the applicant must complete improvements, revegetation measures and soil stabilization prior to plat recording or land use permit, and a professional engineer submits a certification that the improvements were built in accordance with the approved plans.
Two companion rules add detail. Section 70-17.III.H requires all disturbed areas to be revegetated or otherwise mitigated to prevent erosion and dust. Section 70-12 requires a Site Revegetation and Weed Control Plan for projects that involve land disturbance, including subdivisions, major land use permits and any development activity that requires a grading permit, and it demands revegetation with appropriate native plant species approved by the county within no more than one calendar year after substantial completion of soil disturbance, phase by phase on phased projects. For extensive disturbance of more than twenty (20) acres, the county can also require long-term monitoring. Agricultural activities such as cleaning and maintaining ditches and canals are exempt from the weed plan. Section 70-9 itself does not apply to development that needs no land-use permit.
Violations & Fines
Skipping the erosion control plan or building out of line with the approved plan is a violation of the Land Use Code under Section 80-3. The director can send a notice to correct violation with 30 days to comply, or issue a stop order that orders the activity stopped immediately and stays in effect until the director issues a written compliance order. The owner can appeal a stop order to the Board of County Commissioners within three business days. Sanctions can be assessed for each day the violation exists, and the owner pays investigation and hearing costs.
Frequently Asked Questions
What must an erosion control plan show in unincorporated La Plata County?
When does revegetation have to be finished?
Who signs the erosion control plan?
Can a small project skip the plan?
Sources & Official References
Other rules in La Plata County
Compare La Plata County to another location·View the Colorado environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.