La Plata County, CO Environmental Rules: Stormwater Management (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Interior storm drain design storm
10 year storm
Detention check
New impervious area drains to detention in the 100 year storm
Governing standards
Chapter 70 Technical Appendix, Drainage Criteria Standards
Plans sealed by
Professional engineer unless planning engineer waives
Grading contour interval
2 ft up to 20 percent slopes, 10 ft steeper
Completion
Engineer certifies as-built pond volume and orifice size

Summary

In unincorporated La Plata County, Colorado, development needing a land use permit must show it will not adversely affect surface waters by meeting the Chapter 70 Technical Appendix drainage criteria. Land Use Code § 70-9 requires on-site detention, a storm drain design for the ten year storm, and a drainage report signed and sealed by a professional engineer.

These county ordinances apply to unincorporated areas of La Plata County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

I. Purpose and applicability. A. Purpose. ... The purpose of this section is to minimize the potential adverse impacts of development on stormwater quality and quantity for both construction and post-construction runoff. These standards protect the community’s water resources, streams, creeks, rivers, and their availability for existing and future use. ... II. ... Standards. The applicant shall demonstrate the project will not adversely impact surface waters and minimize the potential adverse impacts of development on stormwater quality and quantity for both ... construction and post-construction runoff by meeting the standards found in the Chapter 70 -Technical Appendix, Drainage Criteria Standards. ... ... 4. On-site detention. The applicant shall provide on-site detention to limit the rate of runoff from the site unless exempt based on criteria in subsection 70-9.V. ... ... 6. Storm drain system. The design of the interior storm drain system shall accommodate the ten (10) year storm; however, the design shall direct all drainage from the newly created impervious area to the detention facility during the one hundred (100) year storm.

Full Breakdown

Section 70-9, Grading, Drainage, and Erosion Control, exists to minimize the adverse impacts of development on stormwater quality and quantity for both construction and post-construction runoff, and to protect streams, creeks, rivers and their availability for existing and future use. It applies to all development except development not requiring a land-use permit, wildland fire remediation, plat adjustments and modifications, lot consolidations and boundary adjustments, special events and temporary uses, and additional dwelling units that do not need a major land use permit under section 73-3.

The applicant must demonstrate the project will not adversely impact surface waters by meeting the standards in the Chapter 70 Technical Appendix, Drainage Criteria Standards. The submittal is a set of construction plans, grading plans, erosion control plans and a drainage report, prepared under the direction of and signed and sealed by a professional engineer unless the planning engineer waives that. The planning engineer can waive requirements for minor site improvements, minimal changes in existing drainage patterns or grade, minimal changes in the quantity or quality of stormwater, no need for drainage infrastructure, or a finding that detention is not required. Preliminary documents go in with the project submittal and are revised until approved; final signed and sealed documents are due before construction.

The drainage report carries pre-development and post-development drainage area maps with elevation contours, flow arrows, basin boundaries, labels and areas. Off-site flows must be routed over the detention facility spillway or around the site. The report quantifies pre and post flows, provides on-site detention to limit the rate of runoff unless exempt, describes water quality measures if required, and sizes the interior storm drain system for the ten (10) year storm while directing all drainage from newly created impervious area to the detention facility during the one hundred (100) year storm.

Grading plans must show drainage flowing away from buildings and structures, with contours at two foot intervals up to 20 percent slopes and ten foot intervals on steeper terrain, plus spot elevations, finished floor elevations and culvert inverts. Elevations must come from a survey by a registered surveyor; GIS contour data is not acceptable. For detention projects the engineer's completion letter verifies the constructed pond volume, as-built top of bank and water surface elevations, outlet structure elevations and the orifice size. Where a hazard design alters natural drainage, Section 70-8 requires a drainage easement from impacted downstream owners.

Violations & Fines

Building drainage that departs from the approved plans is a violation of the Land Use Code under Section 80-3, which covers activities inconsistent with a permit or approval. If the public works director or planning engineer does not approve a revision, the applicant must comply with the approved construction plans. The director sends a notice to correct violation with 30 days to comply and can issue a stop order or violation determination, appealable to the Board of County Commissioners. Sanctions can be assessed for each day the violation exists.

Frequently Asked Questions

Which projects in unincorporated La Plata County need a drainage report?
Section 70-9 applies to all development except development not requiring a land-use permit, wildland fire remediation, plat adjustments and modifications, lot consolidations and boundary adjustments, special events and temporary uses, and certain additional dwelling units. The planning engineer can also waive plans and reports for minor site improvements or minimal changes in drainage or grade.
What storm must the drainage design handle?
The interior storm drain system must accommodate the ten year storm. The design must also direct all drainage from newly created impervious area to the detention facility during the one hundred year storm. On-site detention limits the rate of runoff from the site unless the project is exempt under the criteria in subsection V.
Who prepares the drainage plans?
A professional engineer, unless the planning engineer waives the requirement. Documents are signed and sealed, first as preliminary submittals with the project application and then as final submittals before construction. Revisions after approval go to CDD for administrative approval before project completion and must also be signed and sealed.
What happens when construction finishes?
The applicant must complete improvements, revegetation measures and soil stabilization before plat recording or land use permit, and a professional engineer certifies the work matches the approved plans. For projects with detention, the engineer's letter also verifies the constructed pond volume, outlet structure elevations and the orifice in the outlet structure.

Sources & Official References

Other rules in La Plata County

All La Plata County rules

Compare La Plata County to another location·View the Colorado environmental rules overview

Get notified when Stormwater Management in La Plata County, CO changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.