Lacey, WA Environmental Rules: Erosion Control (2026)
Key Facts
- Governing sections
- LMC 14.27.040(D) and 14.27.050
- Required plan
- Core Requirement No. 2: construction SWPPP
- Inspection timing
- Before clearing, during construction, and at completion
- Trigger
- Land-disturbing activity, permit or not
- Appeals
- Chapter 11.05 LMC (LMC 14.27.090)
Summary
In the City of Lacey, Washington, construction sites follow Core Requirement No. 2 of the Stormwater Design Manual, a construction stormwater pollution prevention plan (SWPPP), under LMC 14.27.050. City inspectors check erosion potential before clearing and verify erosion and sediment controls during construction under LMC 14.27.040(D).
14.27.040 Administration and authority. ... D. Inspections. 1. The city shall inspect projects at various stages of the work to determine if they comply with the requirements of this chapter, and enforcement actions shall be taken as necessary. These inspections will include, but not be limited to, the following: a. Prior to site clearing and construction to assess site erosion potential; and b. During construction to verify proper installation and maintenance of required erosion and sediment controls and other approved plan components; and ... 14.27.050 Requirements for new and redevelopment. A. All projects shall comply with the Stormwater Design Manual. ... Core Requirement No. 2: ... Construction stormwater pollution prevention plan (SWPPP). ... 14.27.100 Enforcement. If any person violates or fails to comply with any of these provisions, Chapter 14.40 LMC regarding civil violations shall be applied.
Full Breakdown
Erosion control in the City of Lacey is built into Chapter 14.27 LMC rather than a separate grading chapter. The chapter's stated purpose in LMC 14.27.000 is to set standards for managing stormwater runoff from construction and development sites to minimize degradation of surface water quality by controlling the scouring and sedimentation of creeks, streams, wetlands, ponds, lakes, and other water bodies, and damage to adjacent and downstream private properties from erosion.
LMC 14.27.050 requires all projects to comply with the Stormwater Design Manual, and Core Requirement No. 2 is the construction stormwater pollution prevention plan (SWPPP). LMC 14.27.020(D) applies the chapter to land-disturbing activity on sites that discharge to the city's MS4 or to waters of the state whether or not a city-issued permit is required. Construction counts as started when a grading permit is issued and the related site work has begun.
Inspection is staged. Under LMC 14.27.040(D) the city inspects prior to site clearing and construction to assess site erosion potential, during construction to verify proper installation and maintenance of required erosion and sediment controls and other approved plan components, and on completion before final approval. The applicant also performs special inspection or testing when the city reasonably requires it. Fees follow the schedule established by the city.
Exemptions still carry duties. Pavement maintenance practices that are exempt from the core requirements, such as pothole patching and crack sealing, shall use appropriate BMPs to minimize erosion and sediment transport, and underground utility projects replacing the surface with in-kind material remain subject to Core Requirement No. 2.
Multi-family projects face a second reference: LMC 14.23.080(H)(6) requires storm drainage and erosion control to meet the Drainage Design and Erosion Control Manual for Lacey in the development guidelines.
Violations & Fines
LMC 14.27.100 applies Chapter 14.40 LMC civil violations to any failure to comply with the stormwater chapter. A Notice of Civil Violation schedules a hearings examiner hearing at least ten days later. Penalties are $100 for the first day, $200, $300 and $400 for the next three days, and $500 per day beyond four days. Payment does not relieve the duty to correct the violation.
Frequently Asked Questions
What erosion control plan does a Lacey construction project need?
When does the City of Lacey inspect erosion controls?
Does a small paving job in Lacey need erosion control?
What happens if a contractor fails to keep sediment controls in place in Lacey?
Sources & Official References
Other rules in Lacey
Compare Lacey to another location·View the Washington environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.