Lacey, WA Environmental Rules: Stormwater Management (2026)
Key Facts
- Governing chapter
- Chapter 14.27 LMC, Stormwater Management
- Design standard
- City of Lacey Stormwater Design Manual, nine core requirements
- Private system inspection
- Annually, at the owner's expense
- Catch basin repairs
- Within six months
- Capital construction repairs
- Within two years if greater than $25,000.00
- Appeals
- Chapter 11.05 LMC (LMC 14.27.090)
Summary
In the City of Lacey, Washington, Chapter 14.27 LMC applies to land-disturbing activity and to new, replaced or converted hard surfaces on sites that discharge to the city's MS4 or to waters of the state, whether or not a city permit is required. Privately owned stormwater systems must be inspected annually and maintained by the owner at the owner's expense.
14.27.020 Applicability/regulated activities. ... D. This chapter applies to the following actions on sites that discharge to the city’s MS4 or discharges to waters of the state whether or not a city-issued permit is required: 1. Land-disturbing activity; or 2. Creation of new hard surfaces; or 3. Replacement of existing hard surfaces; ... 6. Any other actions that can increase the volume or rate of stormwater runoff, or cause the generation of pollutants, from the site. ... 14.27.060 Inspection and maintenance of stormwater facilities. ... All privately owned stormwater systems, including flow control and water quality treatment facilities, shall be inspected annually and maintained by the owner at his/her expense. The stormwater system owner shall complete and file an inspection and maintenance form with the city following inspection and maintenance.
Full Breakdown
Chapter 14.27 LMC implements the NPDES Phase II Municipal Stormwater Permit issued by the Washington State Department of Ecology and makes low impact development the preferred and commonly used approach to site development. Under LMC 14.27.020(D) it covers land-disturbing activity, creation, replacement or conversion of hard or pervious surfaces, new connections to the city's MS4, and any other action that can increase the volume or rate of stormwater runoff or generate pollutants.
LMC 14.27.050 requires every project to comply with the City of Lacey Stormwater Design Manual and its nine core requirements: stormwater site plans, a construction SWPPP, source control, preservation of natural drainage systems and outfalls, on-site stormwater management, runoff treatment, flow control, wetlands protection, and operation and maintenance. Submittals carry a Stormwater Site Plan, and where no other city permit applies, review is under a city stormwater permit following the limited administrative review procedure in LMC 11.04.030. Exemptions in LMC 14.27.030 cover forest practices under WAC Title 222 (except Class IV conversions), certain pavement maintenance such as pothole and square cut patching, and underground utility projects that replace the surface with in-kind material.
Maintenance is where owners feel the chapter most. LMC 14.27.060 requires annual inspection of all privately owned stormwater systems, with the owner filing an inspection and maintenance form with the city. A licensed, bonded, and insured contractor must do the work except normal vegetation maintenance. Repairs are due within one year for typical maintenance, within six months for catch basins, and within two years for work requiring capital construction of greater than $25,000.00. Modifications and major repairs need city approval first.
Inspectors present credentials and request entry. Without consent they obtain a search warrant unless an imminent hazard exists or an access easement was dedicated to the city. Government entities are covered by LMC 14.27.070.
Violations & Fines
LMC 14.27.100 applies Chapter 14.40 LMC civil violations to anyone who violates or fails to comply with Chapter 14.27. A Notice of Civil Violation sets a hearings examiner date at least ten days out. Penalties are $100 for the first day, $200, $300 and $400 for days two to four, then $500 per day. The hearing is canceled if the director approves the corrective action 48 hours before it.
Frequently Asked Questions
Who is responsible for maintaining a private stormwater system in the City of Lacey?
How fast must stormwater maintenance be completed in Lacey?
Does Chapter 14.27 apply if no city permit is needed?
Can Lacey inspectors enter private property to check stormwater facilities?
Sources & Official References
Other rules in Lacey
Compare Lacey to another location·View the Washington environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.