Marietta, GA Environmental Rules: Erosion Control (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Governing article
Article 7-8-12, Soil Erosion, Sedimentation and Pollution Control
Permit issuer
Public Works Department
Standard stream buffer
25 feet (50 feet for trout streams)
District plan review window
35 days (Cobb County Soil & Water Conservation District)
Max civil penalty
$2,500 per day per violation
Bond ceiling
$3,000 per acre

Summary

Marietta's Soil Erosion, Sedimentation and Pollution Control Ordinance, City Code Article 7-8-12, requires a public works department permit before land-disturbing activity and mandates best management practices from the state manual on every covered site. A 25-foot vegetated buffer protects state waters, and violators face stop-work orders plus civil penalties of up to $2,500.00 per day.

1.Best management practices as set forth in Sections 7-8-12-040 B. and C. shall be required for all land-disturbing activities. ... 15.Except as provided in paragraphs 16. and 17. of this subsection, there is established a 25-foot buffer along the banks of all state waters, as measured horizontally from the point where vegetation has been wrested by normal stream flow or wave action ... D.Monetary Penalties. Any person who violates any provisions of this article, or any permit condition or limitation established pursuant to this article, or who negligently or intentionally fails or refuses to comply with any final or emergency order of the director issued as provided in this article shall be liable for a civil penalty not to exceed $2,500.00 per day.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 56).

Full Breakdown

Section 7-8-12-050(B) requires a public works department permit, backed by an erosion, sedimentation and pollution control plan, before any land-disturbing activity in the city, along with a copy of any NOI filed with the state Environmental Protection Division. 00 per acre. Section 7-8-12-030 exempts narrow categories: single-family construction disturbing less than one acre and not part of a larger common plan of development, agricultural and forestry operations, Department of Transportation projects, and utility work under Public Service Commission jurisdiction. Section 7-8-12-040(C) sets the substantive standards, including minimizing cut-fill, stabilizing disturbed soil quickly, trapping sediment on-site with basins or silt traps, and, most concretely, a 25-foot buffer along the banks of all state waters measured from the point vegetation has been wrested by normal stream flow, rising to 50 feet along trout streams.

Inspection is handled by the public works department, which can require corrective notice, and the local issuing authority must update its ordinance within 12 months of any change to the state Erosion and Sedimentation Act.

Violations & Fines

A first or second violation draws a written warning with five days to correct; if uncorrected, or on a third violation, the public works department issues an immediate stop-work order under § 7-8-12-070(B). Building without a required permit can also cost the violator's business license or work permit. Section 7-8-12-070(D) makes any violator liable for a civil penalty of up to $2,500.00 per day, enforceable in municipal or magistrate court, with each day of continuing violation a separate offense.

Frequently Asked Questions

Do I need a permit before disturbing land in Marietta?
Yes, unless exempt. Section 7-8-12-050(B)(1) states "no person shall conduct any land-disturbing activity within the jurisdictional boundaries of the city without first obtaining a permit from the public works department," and single-family lots under one acre outside a larger development plan are among the narrow exemptions in § 7-8-12-030.
How wide is Marietta's required stream buffer?
Section 7-8-12-040(C)(15) establishes "a 25-foot buffer along the banks of all state waters, as measured horizontally from the point where vegetation has been wrested by normal stream flow or wave action," rising to 50 feet along streams classified as trout streams under subsection 16.
What penalties apply for erosion control violations?
Section 7-8-12-070(D) makes any violator "liable for a civil penalty not to exceed $2,500.00 per day," with municipal courts authorized to impose that same cap per violation; the city also issues written warnings, five-day correction windows and stop-work orders before penalties escalate under subsection B.

Sources & Official References

Other rules in Marietta

All Marietta rules

Compare Marietta to another location·View the Georgia environmental rules overview

Get notified when Erosion Control in Marietta, GA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.