Medford, MA Environmental Rules: Erosion Control (2026)
Key Facts
- Trigger
- Any excavating, cutting, grading, land-disturbing activity
- Permit issuer
- Director of Public Works or designee
- Plan reviewer
- City Engineer (construction/post-construction plan)
- Waivers
- Only under stormwater regulations (§82-129)
- Section
- Revised Ordinances §82-128
Summary
Any excavating, cutting, grading or other land-disturbing activity in Medford requires a stormwater permit from the director of public works under Revised Ordinances § 82-128, with a construction and post-construction stormwater management plan submitted to the city engineer first.
No person shall excavate, cut, grade or perform any land-disturbing activities without an issued stormwater permit from the director of the department of public works or his/her designee. Prior to the stormwater permit issuance owners of new development and re-development sites shall submit to the city engineer for approval a site construction and post-construction stormwater management plan, in accordance with the requirements and performance standards detailed in the stormwater regulations.
Full Breakdown
Section 82-128, part of the chapter 82 Stormwater System article adopted by Ord. No. 757 in 2010, is Medford's construction-phase erosion and sediment control mechanism. It bars any person from excavating, cutting, grading or performing any land-disturbing activity without an issued stormwater permit from the director of the department of public works or a designee. Before that permit issues, the owner of a new-development or redevelopment site must submit a site construction and post-construction stormwater management plan to the city engineer for approval, meeting the requirements and performance standards set out in the stormwater regulations the stormwater board adopts under § 82-126.
The article's stated purpose in § 82-123, reducing erosion and sedimentation and protecting water quality, frames why the permit exists: without a review of grading and drainage plans before dirt moves, construction sites in Medford would otherwise be free to discharge sediment-laden runoff into the storm drain system that § 82-127 separately prohibits. Waivers or exemptions from any provision of the article, including the § 82-128 permit, are available only as defined in the stormwater regulations and are subject to review and approval by the director of public works under § 82-129.
The director of public works also enforces § 82-128 under § 82-130, with authority to pursue civil or criminal remedies for land-disturbing work performed without the required permit.
Violations & Fines
Excavating, cutting, grading or otherwise disturbing land in Medford without a stormwater permit issued by the director of public works violates § 82-128. The director of public works enforces the requirement under § 82-130 and may pursue civil or criminal remedies; waivers are granted only under the stormwater regulations per § 82-129.
Frequently Asked Questions
Do I need a permit to grade my Medford lot before building?
Can I get a waiver from Medford's stormwater permit?
Who enforces the land-disturbance stormwater permit in Medford?
Sources & Official References
Other rules in Medford
Compare Medford to another location·View the Massachusetts environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.