Key Facts
- Permit trigger
- 1+ acre of land disturbance
- Citation
- Code § 27.5-5
- Small-site exception
- Single-family home under 1 acre
- Plan certifier
- TN engineer or CPESC required
Summary
Murfreesboro requires a land disturbance permit before grading, clearing or filling one acre or more, triggering an Erosion Prevention and Sediment Control plan under Code § 27.5-5 to control runoff, sediment and stabilization during construction.
A land disturbance permit shall be required from the City in the following circumstances:(a)Land disturbing activity disturbs one or more acres of land;(b)Land disturbing activity of less than one acre of land if such activity is part of a larger common plan of development that affects one or more acres of land; see exception in subsection (2) below; or(c)Land disturbing activity of less than one acre of land, if in the opinion of the City, such activity poses a unique threat to water, or to public health or safety.
Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 18 Update 1).
Full Breakdown
Code § 27.5-5 requires a City land disturbance permit whenever land disturbing activity affects one acre or more, is part of a larger common plan of development reaching one acre, or poses a unique water-quality or safety threat regardless of size. A single-family home built alone on less than an acre is exempt from the separate permit but must still meet EPSC standards through its building permit. Larger and public-infrastructure projects must submit an erosion prevention and sediment control plan, certified by a Tennessee engineer or CPESC, detailing site grading, drainage, tree protection and specific control measures, following the City's EPSC-BMP manual and Tennessee's Construction General Permit design storms.
Violations & Fines
Working without a required permit, or failing EP&SC inspections, is enforceable under Chapter 27.5's penalty section: civil fines of $50 to $5,000 per day plus administrative fees up to $5,000.
Frequently Asked Questions
Does building a single house require a separate erosion permit?
What must an EPSC plan include?
Sources & Official References
Other rules in Murfreesboro
Compare Murfreesboro to another location·View the Tennessee environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.