Key Facts

Permit required
Before any land disturbance activity in Murray
NPDES threshold
Disturbance of one acre or more, or part of a larger plan
Notice of intent
To Kentucky Division of Water at least seven days before construction
Bare ground limit
No area left disturbed for more than fourteen days
Plan review
City Engineer acts within 30 days of receipt
Permit fee
No fee is charged for the permit

Summary

In Murray, anyone starting a land disturbance activity needs a city-issued permit, which the city issues once a sedimentation and erosion control plan is submitted and approved under Murray Code of Ordinances § 155.35. Sites of one acre or more fall under NPDES coverage, and no disturbed area may sit bare longer than fourteen days.

(A) Permit required. Prior to any person engaging in a land disturbance activity within the corporate boundaries of the city, they shall possess a city-issued permit for the land disturbance activity. A permit will be issued by the city once a sedimentation and erosion control plan has been submitted and approved. ... (1) Land disturbing activities including development and re-development activities that disturb an area greater than or equal to one (1) acre. ... (3) Submit an electronic notice of intent (NOI) form to the Kentucky Division of Water at least seven (7) days before construction begins. ... (6) Continue to implement all plans and procedures during construction activity, including inspections every seven (7) days, or every 14 days and after each rainfall event of one-half inch or more. ... (6) Disturbed soils shall be stabilized as quickly as possible; however, no area shall be left disturbed for more than fourteen (14) days. (7) Temporary seeding, mulching or other suitable methods of stabilization shall be used to protect exposed areas which have been disturbed longer than 30 days.

Full Breakdown

Section 155.35 requires a city-issued permit before any person engages in land disturbance within Murray's corporate boundaries. The permit follows submission and approval of a sedimentation and erosion control plan, and no fee is charged for it. Activities subject to NPDES coverage include development and re-development that disturbs an area of one acre or more, and smaller sites that are part of a larger common plan of development or sale. The Director of Planning and Engineering or a designee can also pull in sites under one acre that could negatively affect local water quality or sensitive areas.

The operator must submit an erosion and sediment control plan and a Stormwater Pollution Prevention Plan to the City of Murray Planning and Engineering Department, file an electronic notice of intent with the Kentucky Division of Water at least seven days before construction begins, and send the city a copy. Design and maintenance follow the Kentucky Erosion Prevention and Sediment Control Field Guide. Inspections are required every seven days, or every 14 days and after each rainfall event of one-half inch or more, and a signed notice of termination goes to the Division of Water and the city once the site is stabilized.

The plan must be prepared by a licensed professional engineer and show contours at a minimum two foot interval, wetlands, sinkholes, drainage ditches and any one hundred year floodplain on or near the site. The City Engineer reviews it, must act within 30 days of receipt and must give reasons for any denial. An applicant can appeal a denial in writing to the Planning Commission within ten days and is entitled to a hearing within 30 days. Required measures include keeping sediment out of sinkhole throats and outlets, having all controls in place before disturbance, and preventing mud, gravel or debris from reaching public streets or storm drains. Exemptions cover land disturbance for existing one and two family dwellings, home gardening, qualifying agricultural use, and activities under an approved subdivision erosion control plan.

Violations & Fines

Section 155.36 bars a certificate of occupancy for any development until all requirements of Chapter 155 are met. Under § 155.99 the Planning Commission can seek an injunction against subdivision construction, direct the Building Inspector not to issue building permits in the subdivision, and fine violators not less than $10 but not more than $500 for each conviction, with each day a separate offense. Stormwater facilities not kept in working order face corrective action by city forces along with fees and fines.

Frequently Asked Questions

Do I need a permit to grade or clear land in Murray?
Yes. Section 155.35(A) requires a city-issued permit before any land disturbance activity within the corporate boundaries. The city issues it once a sedimentation and erosion control plan is submitted and approved, and no fee is charged. Existing one and two family dwellings, home gardening and qualifying agricultural use are exempt.
How long does Murray take to review an erosion control plan?
The City Engineer must review the plan within 30 days of receipt and notify the applicant, giving reasons for any denial. An applicant can appeal a denial to the Planning Commission in writing within ten days and is entitled to a hearing within 30 days of the appeal.
How long can disturbed soil stay bare?
Section 155.35 says disturbed soils must be stabilized as quickly as possible and that no area shall be left disturbed for more than fourteen days. Temporary seeding, mulching or other suitable stabilization must protect exposed areas disturbed longer than 30 days.
Who must prepare the erosion and sediment control plan?
A licensed professional engineer must prepare the plan, drawn to an appropriate scale, and submit it to the City of Murray Planning and Engineering Department. It must include a project narrative, contours at a minimum two foot interval, grading limits, and delineation of wetlands, sinkholes, drainage ditches and any one hundred year floodplain.

Sources & Official References

Other rules in Murray

All Murray rules

Compare Murray to another location·View the Kentucky environmental rules overview

Get notified when Erosion Control in Murray, KY changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.