FEMA flood zone rules in Murray, KY, also called floodplain regulations or special flood hazard area (SFHA) rules, determine flood insurance requirements and elevation standards for new construction.

Key Facts

Permit trigger
Any construction or development in a special flood hazard area
Who issues forms
The Floodplain Administrator
Mapped basis
FEMA Flood Insurance Study for Murray dated September 29, 2010
As-built certification
Due on placement of the lowest floor, before work continues
Maps on file
Murray City Hall, open to the public in regular business hours
Penalty
Fine of no less than $250 or up to 90 days, or both

Summary

In Murray, no construction or other development may begin inside a FEMA special flood hazard area until the owner holds a development permit issued on forms furnished by the Floodplain Administrator under Murray Code of Ordinances § 152.25. The mapped areas come from the Flood Insurance Study for the City of Murray dated September 29, 2010.

(A) (1) A Development Permit shall be required in conformance with the provision of this chapter prior to the commencement of any development activities in the special flood hazard areas (SFHA). See division (B) for instructions and explanation. (2) Application for a development permit shall be made on forms furnished by the Floodplain Administrator. (B) A development permit shall be obtained before any construction or other development begins within any special flood hazard area established in § 152.08. ... (1) Application stage. (a) Proposed elevation in relation to Mean Sea Level (MSL) of the proposed lowest floor (including basement) of all structures in Zone A and elevation of highest adjacent grade; or ... (d) Description of the extent to which any watercourse will be altered or relocated as a result of proposed development. ... Failure to submit the survey or failure to make said corrections required hereby, shall be cause to issue a stop-work order for the project.

Full Breakdown

Murray regulates building in flood hazard areas through Chapter 152, Flood Damage Prevention. Section 152.08 adopts the areas of special flood hazard identified by FEMA in the Flood Insurance Study for the City of Murray dated September 29, 2010, with the accompanying Flood Insurance Rate Maps and any later amendments, as the minimum area where the chapter applies. The study and maps are kept on file at Murray City Hall and are available to the public during regular business hours. Land the city acquires by annexation is covered as well.

Inside those areas, § 152.25 requires a development permit before any construction or other development begins. Applications go on forms furnished by the Floodplain Administrator and can include scaled plans in duplicate showing the nature, location, dimensions and elevations of the area, existing or proposed structures, fill, storage of materials and drainage facilities. The local administrator's endorsement is required before a state floodplain construction permit can be processed.

The application stage asks for the proposed lowest floor elevation (including basement) relative to Mean Sea Level in Zone A, the elevation of the highest adjacent grade, or the floodproofing elevation for a non-residential structure, plus engineer or architect certification of floodproofing and a description of how any watercourse will be altered or relocated. At the construction stage, once the lowest floor is placed and before work continues, the permit holder must send the Floodplain Administrator and the state an as-built elevation certification. In AE, A1-30, AH and A zones where Murray has adopted a regulatory Base Flood Elevation, a registered land surveyor or professional engineer must prepare it. Continued work before the certification is at the permit holder's risk, and failure to submit the survey or to correct deficiencies is cause for a stop-work order. Section 152.10 provides that where Chapter 152 and another ordinance, easement, covenant or deed restriction conflict or overlap, whichever imposes the more stringent restrictions prevails.

Violations & Fines

Development in Murray that departs from Chapter 152, including work without the permit or in breach of its conditions, is a misdemeanor criminal offense under §§ 152.07, 152.57 and 152.99. An employee of the Floodplain Administrator issues a notice stating the facts, the section violated, how to cure it and a reasonable deadline, and the remedy can include a stop-work order. On conviction § 152.99 sets a fine of no less than $250 or imprisonment of not more than 90 days, or both, plus costs, and each day the violation continues is a separate offense.

Frequently Asked Questions

Do I need a permit to build in a flood zone in Murray?
Yes. Section 152.25 requires a development permit before any construction or other development begins within a special flood hazard area established in § 152.08. Application is made on forms furnished by the Floodplain Administrator, with plans showing the nature, location, dimensions and elevations of the area and any structures, fill or drainage facilities.
Where can I see the flood maps Murray uses?
Section 152.08 adopts the FEMA Flood Insurance Study for the City of Murray dated September 29, 2010, and its Flood Insurance Rate Maps. They are permanent records of Murray, on file at Murray City Hall and available for public review during regular business hours.
What happens if I do not submit the elevation certification?
Under § 152.25(B)(2), the permit holder must certify the as-built lowest floor or floodproofed elevation once the lowest floor is placed. Work continued before the certification is at the permit holder's risk, and failing to submit the survey or correct deficiencies is cause for a stop-work order.
What is the penalty for building in a flood area without a permit?
It is a misdemeanor criminal offense. Section 152.99 sets a fine of no less than $250 or imprisonment of not more than 90 days, or both, plus costs, and each day counts separately. Section 152.57 also lets the Floodplain Administrator's staff issue a notice requiring a remedy within a reasonable time.

Sources & Official References

Other rules in Murray

All Murray rules

Compare Murray to another location·View the Kentucky environmental rules overview

Get notified when Flood Zones in Murray, KY changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.