Murray, KY Environmental Rules: Stormwater Management (2026)
Key Facts
- Permit trigger
- Any land disturbance within city limits
- Acreage threshold
- One acre or more, or part of a larger common plan
- NOI to Kentucky Division of Water
- At least seven days before construction begins
- Site inspections
- Every seven days, or every 14 days and after rainfall of one-half inch
- Civil penalty
- $250 per violation per day
- Plan preparer
- Licensed professional engineer
- Water quality design event
- 80th percentile precipitation event
Summary
Murray requires a city-issued permit before any land disturbance within the city limits, issued once a sedimentation and erosion control plan is approved. Section 156.095 covers sites of one acre or more, requires inspections every seven days, and § 156.999(C) sets a civil penalty of $250 per violation per day.
(A) Permit required. Prior to any person engaging in a land disturbance activity within the corporate boundaries of the city, they shall possess a city-issued permit for the land disturbance activity. A permit will be issued by the city once a sedimentation and erosion control plan has been submitted and approved. ... (1) Land disturbing activities including development and re-development activities that disturb an area greater than or equal to one (1) acre. Sites that are smaller than one (1) acre are also covered by this subchapter if they are part of a larger common plan of development or sale. ... (3) Submit an electronic notice of intent (NOI) form to the Kentucky Division of Water at least seven (7) days before construction begins. ... (6) Continue to implement all plans and procedures during construction activity, including inspections every seven (7) days, or every 14 days and after each rainfall event of one-half inch or more.
Full Breakdown
Stormwater and erosion control in Murray sit in the zoning code's storm water subchapter, §§ 156.090 through 156.097. Section 156.095(A) requires a person to possess a city-issued permit before engaging in any land disturbance activity within the corporate boundaries, and the city issues it once a sedimentation and erosion control plan has been submitted and approved. Section 156.095(B)(1) covers disturbances of an area greater than or equal to one (1) acre, plus smaller sites that are part of a larger common plan of development or sale. Under (B)(2), the Director of Planning and Engineering or a designee can also bring in sites under one acre that have the potential to negatively impact local water quality or sensitive areas, at his or her sole discretion.
Permit coverage under the NPDES general permit adds a series of steps in § 156.095(C): submit an erosion and sediment control plan and a Stormwater Pollution Prevention Plan to the City of Murray Planning and Engineering Department; file an electronic notice of intent with the Kentucky Division of Water at least seven (7) days before construction begins; keep implementing the plans during construction, with inspections every seven (7) days, or every 14 days and after each rainfall event of one-half inch or more; and submit a signed notice of termination after the site is stabilized. Under (D), the plan must be prepared by a licensed professional engineer.
Design standards are in § 156.093. Open channels and roadside ditches use a ten year/24-hour storm. Storm sewers, inlets, entrance pipes and cross drains use the 25-year storm/24-hour duration, and the ponding limit for streets with curb and gutter is an eight-foot spread. Culverts are designed for the 25-year storm, with the 100-year storm as the recommended check. Water quality structures are sized to the 80th percentile precipitation event, and all conveyance and water quality design must be stamped by a Kentucky-registered professional engineer.
Section 156.097(E) bars any person from discharging into the storm drainage system anything other than stormwater, with listed exceptions. Under § 156.096, no certificate of occupancy issues until the chapter's requirements are fully met.
Violations & Fines
Under § 156.999(C), any person subject to §§ 156.090 through 156.097 is liable to the city for a civil penalty of $250 per violation per day for as long as the violation continues. The city can also recover reasonable attorney fees, court costs and other expenses incurred in any enforcement proceedings. The authorized enforcement agency is defined in § 156.091 as the Mayor, City of Murray, MS4 Operator or authorized representative. Section 156.096 withholds the certificate of occupancy from any development that has not met the chapter's requirements.
Frequently Asked Questions
Do I need a permit to grade my lot in Murray?
What does Murray require during construction?
What is the penalty for violating Murray's stormwater rules?
Can I send something other than stormwater into a Murray storm drain?
Sources & Official References
Other rules in Murray
Compare Murray to another location·View the Kentucky environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.