Key Facts

Plan required
Erosion control plan with a grading or pollution-source permit
SWPPP
Submitted before permit issuance; approved by Public Works Director
Inadequate controls
No other site work until controls are in place
Hillside grading
Slopes of 10 percent or more; over 30 percent needs approval
Erosion standards
Storm Water Management Plan, regional field manual, NPDES, CALGreen
Stop work order
Issued until BMPs are implemented or maintained

Summary

In the City of Pismo Beach, California, a project with a grading permit or any other permit likely to create a pollution source must submit an erosion control plan. On a construction site with inadequate erosion and sediment controls, the director gives verbal notice and issues a notice of violation, and the city allows no other site work until the controls are in place.

E. Compliance. ... A person with a project that includes a grading permit or any other permit that is likely to create a source of pollution shall submit an erosion control plan. ... ... B. Construction sites. The director shall give verbal notice and issue a notice of violation to persons owning or controlling construction sites with inadequate erosion and sediment controls that such controls must be put in place immediately, and the city shall not allow any other site work until the controls are in place. ... J110.3 Other standards. Erosion control measures shall conform to the following standards and approval processes: 1. The City of Pismo Beach Storm Water Management Plan. 2. The most current "Erosion and Sediment Control Field Manual" published by the California Regional Water Quality Control Board, San Francisco Bay Region. 3. NPDES permit requirements. 4. The 2025 California Green Building Standards Code.

Full Breakdown

Erosion control in the City of Pismo Beach comes from two places: the Stormwater Quality Ordinance in Chapter 13.28 and the grading appendix the city adds to its building code in § 15.08.010.

Under § 13.28.150, a person with a project that includes a grading permit or any other permit likely to create a source of pollution submits an erosion control plan. Before the city issues a permit for activities that could contribute to pollution of the storm drain system, the applicant must also submit a storm water pollution prevention plan, called a SWPPP, which the Public Works Director approves. The SWPPP is a living document that must be adjusted during construction to meet unforeseen conditions and changing work. If BMPs are inadequate, an illegal discharge results and the permit holder fails to fix it immediately after notice, the city issues a stop work order until it is fixed (§ 13.28.150 E). Section 13.28.160 B repeats the stop work consequence for failing to maintain construction BMPs.

Section 13.28.260 B is the hard stop: at a construction site with inadequate erosion and sediment controls, the director gives verbal notice and issues a notice of violation, and the city allows no other site work until the controls are in place.

The grading appendix in § 15.08.010 adds site rules. Erosion control measures must conform to the City of Pismo Beach Storm Water Management Plan, the Erosion and Sediment Control Field Manual published by the California Regional Water Quality Control Board, San Francisco Bay Region, NPDES permit requirements and the 2025 California Green Building Standards Code (J110.3). Hillside areas are properties with slopes of 10 percent or more, and no grading starts on slopes greater than 30 percent unless the Planning Commission or City Council approves (J101.3). Building construction cannot start until the building official or city engineer verifies that rough grading conforms to the approved plan, including any interim or permanent erosion control measures deemed necessary (J101.4). For subdivisions, § 16.52.020 conditions every approved map on grading and erosion control, including prevention of sedimentation or damage to off-site property and wildlife habitats.

Violations & Fines

A violation of Chapter 13.28 is a misdemeanor punishable under Chapter 1.20, with fines under Chapter 1.24, possible business license revocation and, for work in the right-of-way, a two-year work ban (§ 13.28.280 B). Continuing work after a building stop work order brings penalties under Chapters 1.20, 1.24 and 1.28 (§ 15.08.010, Section 115.4). If a notice of violation is not complied with, the city can abate the condition and charge the property owner.

Frequently Asked Questions

When do I need an erosion control plan in Pismo Beach?
Section 13.28.150 E requires an erosion control plan from a person with a project that includes a grading permit or any other permit that is likely to create a source of pollution. The requirement sits alongside the SWPPP that must be submitted before the city issues any permit for activities that could contribute to pollution of the storm drain system.
What is a SWPPP and who approves it?
A storm water pollution prevention plan identifies sources of pollution and directs the contractor and owner in using BMPs to prevent pollution during construction (§ 13.28.030). Under § 13.28.150 C the Public Works Director approves it once satisfied it meets the chapter, and it must be adjusted during construction as conditions and work change.
What happens if my site has no sediment controls?
Under § 13.28.260 B the director gives verbal notice and issues a notice of violation, the controls must go in immediately, and the city allows no other site work until they are in place. Under § 13.28.150 E and § 13.28.160 B, a permit holder who fails to implement or maintain BMPs after notice faces a stop work order.
Can I grade a steep lot?
Hillside areas are properties with slopes of 10 percent or more. Under Appendix Section J101.3 in § 15.08.010, no grading starts on slopes greater than 30 percent, including access roads and driveways, unless the Planning Commission or City Council approves, and the city zoning ordinance hillside regulations apply in addition to the building code standards.

Sources & Official References

Other rules in Pismo Beach

All Pismo Beach rules

California rules heatmap·Compare Pismo Beach to another location·View the California environmental rules overview

Get notified when Erosion Control in Pismo Beach, CA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.