Saint Paul, MN Environmental Rules: Erosion Control (2026)
Key Facts
- Permit trigger
- >50 cubic yards of fill
- Governing standard
- Appendix E, 2007 MN Building Code
- Site plan review trigger
- >10,000 sq ft graded
- Fill type
- Clean fill only
- Starting fee
- $39.00 for first 100 cu yd
- Penalty
- Misdemeanor under § 33.09
Summary
Saint Paul requires a grading permit before moving more than fifty cubic yards of fill, and every grading job must follow Appendix E of the 2007 Minnesota State Building Code. Larger sites trigger site plan review, and only clean fill may be placed on the property.
No person shall perform any filling or excavating activity on a property unless such activity is in accordance with the provisions of Appendix E (Grading) of the 2007 Minnesota State Building Code, as amended from time to time, and the requirements herein. Unless grading activity is included in a general building permit, a grading permit shall be required for the placement, removal or movement of more than fifty (50) cubic yards of fill. Only clean fill may be deposited as fill material on the property. Grading activities in excess of ten thousand (10,000) square feet require site plan review in accordance with section 61.402(a) of the Saint Paul Legislative Code. The property owner and/or permittee shall be responsible for the grading on site.
Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 133 Update 1).
Full Breakdown
03(g) sets Saint Paul's grading and drainage permit framework inside the building permits chapter rather than a separate public-works ordinance. No person may perform filling or excavating activity on a property unless the work follows Appendix E (Grading) of the 2007 Minnesota State Building Code, as amended, and the additional local requirements in this subsection. A grading permit is required whenever the placement, removal or movement of more than fifty cubic yards of fill is not already covered by a general building permit, so a homeowner regrading a small backyard slope under that threshold may not need a separate grading permit, but anything larger does.
Only clean fill may be deposited as fill material on the property; contaminated or mixed debris fill is not permitted under this section. 402(a) of the Saint Paul Legislative Code before work can proceed. The property owner and/or the permittee is responsible for the grading on site, meaning liability for drainage problems or erosion runs with both the landowner and whoever pulls the permit. 00 per additional 10,000 cubic yards.
Violations & Fines
Grading without the required permit, or grading that doesn't follow Appendix E of the state building code, is a misdemeanor under Saint Paul Legislative Code § 33.09. The building official can stop work, require corrective grading, and hold the property owner and permittee jointly responsible for restoring drainage or erosion damage caused by noncompliant grading.
Frequently Asked Questions
Do I need a permit to regrade my yard in Saint Paul?
What standard does Saint Paul grading work have to meet?
How much does a Saint Paul grading permit cost?
Sources & Official References
Other rules in Saint Paul
Compare Saint Paul to another location·View the Minnesota environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.