Key Facts

Permit trigger: fill
Over 3 feet
Permit trigger: excavation
Over 5 feet
Permit trigger: grading/clearing
5,000 sq ft or more
Entrance protection distance
25 feet from public roadway
Permit validity
1 year, renewable
Issuing agency
Polk County Public Works

Summary

Unincorporated Polk County requires a Grading Permit for land-disturbing work exceeding three feet of fill, five feet of excavation, or 5,000 square feet of grading or clearing. The Zoning Ordinance's erosion and sediment control division adopts Iowa DNR's construction erosion standards by reference and Public Works issues and enforces the permit.

City-specific rules exist: Des Moines has its own erosion control rules that differ from Polk County's county-level regulations. If you live in Des Moines, check the city-specific page instead.

Section 2. Applicability

No person shall engage in land-disturbing activities that include fill in excess of three (3) feet, excavation exceeding five (5) feet or any grading or clearing activity that disturbs an area of five thousand (5,000) square feet within the unincorporated parts of Polk County unless they have received a Grading Permit. In addition, through the Iowa DNR, owners of certain construction sites are required to obtain permit coverage under rules contained in National Pollutant Discharge Elimination System General Permit No. 2, Storm Water Discharge Associated with Industrial Activity for Construction Activities ("General Permit No. 2").

View official code

Official source re-checked September 7, 2026: the cited page had not changed since it was quoted.

Full Breakdown

Article 8, Division 2, Section 1 explains the rationale: uncontrolled soil erosion damages drainageways, raises road and storm sewer maintenance costs, endangers roadways and pollutes streams. Section 2 sets the applicability trigger at fill over three feet, excavation over five feet, or any grading or clearing disturbing 5,000 square feet, and separately flags that some construction sites also need Iowa DNR coverage under NPDES General Permit No. 2. Section 3 adopts the Iowa DNR's Construction Site Erosion Control Manual by reference, requires perimeter protection and a gravel entrance drive at least 25 feet from the public roadway on any soil-disturbing job, though the Zoning Administrator may waive that if existing ground cover doesn't warrant it, or demand more protection if what's in place isn't working.

Section 4 puts Public Works in charge of issuing permits, requires the application to be signed by the title holder, and includes a Grading Plan from a licensed engineer (unless waived), a SWPPP, and the permit fee; the permit is valid one year and must be renewed with updated information and fee. Section 5 layers in extra permits for floodplain filling, but waives a separate Grading Permit where the work is already covered by a Demolition or Building Permit with an approved NPDES SWPPP. Section 6 exempts crop production, cemetery graves, life-safety emergencies, and public improvements from the permit requirement entirely.

Violations & Fines

As a zoning permit requirement, unpermitted grading is enforced under Article 23: the Zoning Administrator serves written notice with a correction deadline, and each day of continued violation counts separately. Failure to comply after a Notice of Violation brings a citation with up to 30 days to fix it, and the county can order a stop-work order, block further permits on the property, and pursue civil or criminal remedies or injunctive relief.

Frequently Asked Questions

When do I need a Grading Permit in unincorporated Polk County?
When your project fills more than 3 feet, excavates more than 5 feet, or grades or clears 5,000 square feet or more of land, per Section 2. Some construction sites separately need Iowa DNR permit coverage under NPDES General Permit No. 2.
What has to be submitted with a Grading Permit application?
A completed application, a Grading Plan from a licensed engineer unless the Zoning Administrator waives it, a SWPPP meeting this chapter and NPDES General Permit No. 2, and the permit fee, per Section 4. Permits run one year and must be renewed.
Is any work exempt from the Grading Permit requirement?
Yes. Section 6 exempts crop production activities, cemetery graves, emergencies posing immediate danger to life, property, flood or fire hazards, and public improvements from needing a permit under this chapter.

Sources & Official References

Other rules in Polk County

All Polk County rules

Compare Polk County to another location·View the Iowa environmental rules overview

Get notified when Erosion Control in Polk County, IA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Erosion Control in Cities Across Polk County