Seaside, OR Environmental Rules: Erosion Control (2026)
Key Facts
- General trigger
- Land disturbance over 1000 square feet
- Near water
- Over 500 square feet within 25 feet of a stream, watercourse or wetland
- Cut or fill
- 20 cubic yards on lots of 5000 square feet or less; 50 cubic yards on larger lots
- Stabilization deadline
- 7 calendar days after active disturbance ends
- Reviewing office
- Department of Building and Code Enforcement
- Maximum penalty
- 30 days in jail or $150.00 fine, or both
Summary
In Seaside, no one can start clearing, grading, stripping, excavation or fill above set thresholds without an approved Grading and Erosion Control Plan from the Department of Building and Code Enforcement. The triggers are 1000 square feet of disturbance, 500 square feet within 25 feet of a stream, watercourse or wetland, or 20 or 50 cubic yards of cut or fill.
Section 4.201 Purpose: It is the objective of this ordinance to control activities that lead to soil erosion and sedimentation into watercourses, wetlands, riparian areas, public and private roadways caused by development activities, including clearing, grading, stripping, excavating, and filling of land. ... 1. Grading and Erosion Control Plan Required Except as otherwise provided in this ordinance, no person shall commence or perform any activities described in 4.202 a-c without receiving approval of a Grading and Erosion Control Plan by the City of Seaside Department Building and Code Enforcement. A. Any land disturbing activity (i.e. clearing, grading, stripping, excavation, fill, or any combination thereof) that will affect an area in excess of 1000 square feet; B. Any land disturbing activity that will affect an area in excess of 500 square feet if the activity is within 25 feet of a stream, watercourse, or wetland; or C. An excavation, fill, or any combination thereof that will exceed 20 cubic yards on a lot or parcel that is less than or equal to 5000 square feet or 50 cubic yards on a lot or parcel that is greater than 5000 square feet.
Full Breakdown
Section 4.201 states the objective: to control activities that lead to soil erosion and sedimentation into watercourses, wetlands, riparian areas, and public and private roadways caused by clearing, grading, stripping, excavating and filling of land. Section 4.202 then requires an approved plan for any land disturbing activity affecting an area in excess of 1000 square feet; any such activity affecting more than 500 square feet within 25 feet of a stream, watercourse or wetland; or an excavation or fill exceeding 20 cubic yards on a lot of 5000 square feet or less, or 50 cubic yards on a larger lot.
Three activities are exempt: cutting brush where ground cover will remain intact, routine maintenance of road drainage ditches by City Public Works employees, and emergency measures taken to clear roadways or to save endangered property.
The owner or the owner's agent submits the plan to the Department of Building and Code Enforcement on a site plan at a scale of one (1) inch equals ten (10) feet. The plan shows adjacent roads, nearby watercourses, vegetation to be kept, contours at intervals of two (2) feet, soil stockpiles, the type and location of erosion control measures, a construction schedule, and the person responsible for placing and maintaining the measures. The Department then approves the submittal, approves it with reasonable conditions, or disapproves it and states the appeal or revision procedure.
Section 4.204 sets the field standards. Filter barriers must be constructed and functional before work starts, with vegetated strips at least 25 feet wide allowed only where sheet flow is expected. Disturbed areas must be stabilized within 7 calendar days after active disturbance ends, and slopes greater than 12 percent need sod, mat or blanket with seeding. Soil piles of more than 10 cubic yards cannot sit within a downslope drainage length of less than 25 feet to a roadway or drainage channel. Sediment reaching a roadway must be removed by shoveling or street cleaning, not flushing, before the end of each workday, and temporary measures come out within 30 days after final site stabilization. Landowners or their agents inspect measures every 24 hours during storm or rain events.
Violations & Fines
A violation of the Zoning Ordinance is punishable on conviction by imprisonment for not more than thirty (30) days or a fine of not more than $150.00, or both, and each day is a separate offense (Section 12.010). Section 12.020 treats work in violation as a nuisance that the City can enjoin or abate. The Department of Building and Code Enforcement makes regular inspections of erosion control measures.
Frequently Asked Questions
When do I need an erosion control plan in Seaside?
Who approves the plan?
What work is exempt?
How fast must bare soil be covered?
Sources & Official References
Other rules in Seaside
Compare Seaside to another location·View the Oregon environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.