Seaside, OR Environmental Rules: Stormwater Management (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified November 2026

Key Facts

Plan required
Land disturbance over 1000 square feet
Near streams or wetlands
Over 500 square feet within 25 feet of a stream, watercourse or wetland
Excavation or fill trigger
Over 20 cubic yards on lots of 5000 square feet or less; over 50 on larger lots
Reviewing office
Department of Building and Code Enforcement
Stabilizing bare soil
Within 7 calendar days after active disturbance ends
Inspection during storms
Landowner or agent inspects erosion controls every 24 hours
Sanitary sewer
Stormwater and roof runoff barred (§ 51.017(A))

Summary

In Seaside, land disturbance over 1000 square feet needs an approved Grading and Erosion Control Plan from the Department of Building and Code Enforcement, and the threshold drops to 500 square feet within 25 feet of a stream, watercourse or wetland. Storm sewer inlets and culverts must be protected, and stormwater cannot be sent to a sanitary sewer.

Except as otherwise provided in this ordinance, no person shall commence or perform any activities described in 4.202 a-c without receiving approval of a Grading and Erosion Control Plan by the City of Seaside Department Building and Code Enforcement. A. Any land disturbing activity (i.e. clearing, grading, stripping, excavation, fill, or any combination thereof) that will affect an area in excess of 1000 square feet; B. Any land disturbing activity that will affect an area in excess of 500 square feet if the activity is within 25 feet of a stream, watercourse, or wetland; or C. An excavation, fill, or any combination thereof that will exceed 20 cubic yards on a lot or parcel that is less than or equal to 5000 square feet or 50 cubic yards on a lot or parcel that is greater than 5000 square feet. ... D. Storm sewer inlets and culverts shall be protected by sediment traps or filter barriers meeting accepted design standards and specifications. ... The landowner or their agent shall inspect erosion control measures every 24 hours during storm or rain events to ensure the erosion control measures are functioning properly.

Full Breakdown

Seaside controls stormwater impacts mainly through the grading and erosion control provisions of Article 4 of Zoning Ordinance 83-10. The stated objective in § 4.201 is to control activities that lead to soil erosion and sedimentation into watercourses, wetlands, riparian areas and public and private roadways caused by development activities, including clearing, grading, stripping, excavating and filling of land.

Under § 4.202(1), no person can start those activities without an approved Grading and Erosion Control Plan from the Department of Building and Code Enforcement when the work affects an area in excess of 1000 square feet, affects an area in excess of 500 square feet within 25 feet of a stream, watercourse or wetland, or involves excavation or fill exceeding 20 cubic yards on a lot of 5000 square feet or less, or 50 cubic yards on a larger lot. Exemptions cover cutting brush where ground cover remains intact, routine maintenance of road drainage ditches by City Public Works employees, and emergency measures to clear roadways or save endangered property. The owner or agent submits the plan on a site plan at a scale of one inch equals ten feet, showing among other items the direction of surface water flows, slope contours at two-foot intervals, soil stockpiles, and the type and location of erosion control measures. The Department then approves, approves with conditions, or disapproves in writing.

Section 4.204 sets the field standards. On-site erosion control measures must be constructed and functional before clearing or grading starts. Disturbed areas must be stabilized within 7 calendar days of the end of active disturbance, and areas with slopes greater than 12 percent need sod, mat or blanket in combination with seeding. Storm sewer inlets and culverts are protected by sediment traps or filter barriers, and sediment reaching a roadway is removed by shoveling or street cleaning, not flushing, before the end of each workday.

Two other chapters address runoff. Section 51.017 bars discharging stormwater, surface water, ground water or roof runoff to any sanitary sewer and directs it to combined or storm sewers, or to a natural outlet approved by the Superintendent. Section 96.19 bars letting rainwater, ice or snow fall from a building onto a street or public sidewalk, and bars draining overflow water onto another person's property.

Violations & Fines

Section 51.999(A) makes continuing a sewer-chapter violation past the stated time limit a misdemeanor with a fine not exceeding $500 for each violation, each day a separate offense, and division (B) allows a fine of not more than $500, imprisonment for not more than 180 days, or both. Violations of the nuisance chapter, including § 96.19 drainage, are misdemeanors with a fine not to exceed $700, each day separate (§ 96.99). The Department of Building and Code Enforcement makes regular inspections of erosion controls.

Frequently Asked Questions

When does a Seaside project need a Grading and Erosion Control Plan?
Section 4.202(1) requires approval from the Department of Building and Code Enforcement before land disturbance affecting an area in excess of 1000 square feet, or in excess of 500 square feet within 25 feet of a stream, watercourse or wetland. It also applies to excavation or fill exceeding 20 cubic yards on a lot of 5000 square feet or less, or 50 cubic yards on a larger lot.
What work is exempt from the erosion control plan?
Section 4.202(2) exempts three activities: cutting brush where ground cover will remain intact, routine maintenance of road drainage ditches by City Public Works employees, and emergency measures taken to clear roadways or to save endangered property. Everything else that crosses the size thresholds in § 4.202(1) needs the approved plan before work begins.
How fast must bare soil be stabilized in Seaside?
Under § 4.204(2)(B), disturbed areas must be stabilized with temporary or permanent measures within 7 calendar days, or as otherwise required by the Building Inspector, after active disturbance ends. Slopes greater than 12 percent need sod, mat or blanket combined with seeding. Riparian areas need erosion protection within 24 hours of disturbance, or up to 48 hours at the Building Inspector's discretion.
Can I connect a roof drain to the sanitary sewer in Seaside?
No. Section 51.017(A) bars any person from discharging stormwater, surface water, ground water, roof runoff, subsurface drainage, uncontaminated cooling water or unpolluted industrial process waters to any sanitary sewer. Under § 51.017(B), stormwater and other unpolluted drainage go to sewers specifically designated as combined sewers or storm sewers, or to a natural outlet approved by the Superintendent.

Sources & Official References

Other rules in Seaside

All Seaside rules

Compare Seaside to another location·View the Oregon environmental rules overview

Get notified when Stormwater Management in Seaside, OR changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.