Key Facts

Governing law
Chapter 152 as replaced by Ordinance No. 2025-04
Permit trigger
Any development in a special flood hazard area, including fill
Flood maps adopted
Clatsop County FIS dated June 20, 2018, with FIRMs
Floodplain Administrator
Community Development Director
Maps on file
City Hall, 989 Broadway, Seaside
Penalty
Misdemeanor: fine up to $500.00, up to 180 days, or both

Summary

Seaside requires a floodplain development permit before construction or development begins anywhere in a special flood hazard area, covering all structures, manufactured dwellings and other development including fill. Ordinance No. 2025-04 repealed and replaced Chapter 152, and a violation is a misdemeanor punishable by a fine of not more than $500.00, imprisonment up to 180 days, or both.

The special flood hazard areas identified by the Federal Insurance Administrator in a scientific and engineering report entitled "The Flood Insurance Study (FIS) for Clatsop County Oregon and Incorporated Areas Volume 1 & 2 dated June 20, 2018, with accompanying Flood Insurance Rate Maps (FIRMs) are hereby adopted by reference and declared to be a part of this ordinance. ... shall constitute a misdemeanor. Any person who violates the requirements of this ordinance shall, upon conviction thereof, be fined not more than $500.00 or imprisonment for a period not to exceed 180 days or both. ... A development permit shall be obtained before construction or development begins within any area horizontally within the special flood hazard area established in Section 152.3.2. The development permit shall be required for all structures, including manufactured dwellings, and for all other development, as defined in Section 152.2.0, including fill and other development activities.

Full Breakdown

Chapter 152, Flood Damage Prevention, was repealed and replaced by Ordinance No. 2025-04, whose recitals explain why: on July 15, 2024, FEMA notified Seaside that it must select and apply a Pre-Compliance Implementation Measure to all floodplain development, which required revisions to the city's ordinance. The replacement chapter applies to all special flood hazard areas within the city (§ 152.3.1). Those areas are the ones identified in the Flood Insurance Study for Clatsop County Oregon and Incorporated Areas dated June 20, 2018, with its Flood Insurance Rate Maps, which are adopted by reference, and the FIS and FIRM panels are on file at City Hall at 989 Broadway (§ 152.3.2). The chapter is administered and enforced in conjunction with the Oregon Specialty Codes (§ 152.3.3).

The Community Development Director is appointed Floodplain Administrator, administers and enforces the chapter by granting or denying development permits, and can delegate authority (§ 152.4.1). Section 152.4.3.1 requires a development permit before construction or development begins within the special flood hazard area, for all structures including manufactured dwellings and for all other development as defined in § 152.2.0, including fill. The application is made on forms the Floodplain Administrator furnishes, with plans drawn to scale showing the nature, location, dimensions and elevations of the area, plus the items listed in § 152.4.3.2: the proposed lowest floor elevation in riverine zones, the elevation of the bottom of the lowest structural member in coastal zones, the floodproofing elevation and an engineer or architect certification for non-residential floodproofing, a description of any watercourse alteration, base flood elevation data for subdivisions, a substantial improvement calculation, and the amount and location of any fill or excavation. In reviewing permits the administrator confirms that all other required local, state and federal permits have been obtained and checks whether the proposal lies in a floodway (§ 152.4.2.1).

A variance is for floodplain management purposes only and does not change federal flood insurance premium rates (§ 152.4.4). An applicant granted a variance to build below the Base Flood Elevation receives written notice that insurance premium rates will increase (§ 152.4.4.2).

Violations & Fines

Failure to comply with the chapter, including violations of conditions and safeguards attached to a permit, is a misdemeanor. On conviction a person is fined not more than $500.00 or imprisoned for a period not to exceed 180 days or both (§ 152.3.4.2). The same section bars constructing, locating, extending, converting or altering any structure or land without full compliance, and it does not prevent the city from taking any other lawful action needed to prevent or remedy a violation.

Frequently Asked Questions

Do I need a permit to fill land in a Seaside flood zone?
Yes. Section 152.4.3.1 requires a development permit before construction or development begins within the special flood hazard area. It applies to all structures, including manufactured dwellings, and to all other development as defined in § 152.2.0, including fill and other development activities. The application must state the amount and location of any fill or excavation proposed (§ 152.4.3.2).
Who issues floodplain permits in Seaside?
The Community Development Director, who is appointed Floodplain Administrator in § 152.4.1 to administer, implement and enforce the chapter by granting or denying development permits. The administrator can delegate authority to implement the provisions. Review includes confirming that other required local, state and federal permits are in hand and whether the proposal sits in a floodway (§ 152.4.2.1).
Where can I see Seaside's flood maps?
The special flood hazard areas are those identified in the Flood Insurance Study for Clatsop County Oregon and Incorporated Areas dated June 20, 2018, with its Flood Insurance Rate Maps, adopted by reference in § 152.3.2. The FIS and FIRM panels are on file at City Hall at 989 Broadway, Seaside, OR, 97138.
What is the penalty for breaking Seaside's flood rules?
A violation is a misdemeanor. Under § 152.3.4.2, a person who violates the requirements is, on conviction, fined not more than $500.00 or imprisoned for a period not to exceed 180 days or both. The city also keeps the power to take any other lawful action necessary to prevent or remedy the violation, so a fine does not end the matter.
Does a variance lower my flood insurance in Seaside?
No. Section 152.4.4 says a variance is issued for floodplain management purposes only, and flood insurance premium rates are determined by federal statute according to actuarial risk and will not be modified by granting a variance. A person granted a variance to build below the Base Flood Elevation gets written notice that premium rates will increase (§ 152.4.4.2).

Sources & Official References

Other rules in Seaside

All Seaside rules

Compare Seaside to another location·View the Oregon environmental rules overview

Get notified when Flood Zones in Seaside, OR changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.