Key Facts
- Plan required before
- Any construction activity begins
- Approving official
- County engineer or designee
- Max graded slope
- Capped at 4:1 or less
- Stabilization deadline
- 10 working days after grading phase
- State permit trigger
- 1 acre or more disturbed
- Exempt uses
- Emergency work, permitted mining, existing agriculture
Summary
St. Lucie County requires an approved erosion and sediment control plan before any construction activity begins, under Article VI, Division 2 of the county code. Sites must stabilize graded slopes within ten working days, control clearing until sediment devices are installed, and secure construction waste to keep silt out of drainage systems and water bodies.
No person may engage in construction activity until a plan has been submitted for erosion and sediment control and such plan has been approved by the county engineer or designee. The plan must address all applicable BMPs for erosion control and shall include a statement that any land clearing, construction, or development involving the movement of earth shall be in accordance with the erosion and sediment control plan and that a certified contractor shall be on site on all days when land disturbing activity takes place.
Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 32 | Land Development Code: Supplement 36).
Full Breakdown
Division 2 of Article VI, sections 20-180 through 20-183, sets the county's construction-site erosion rules, adopted on findings that disturbed soil is highly vulnerable to erosion by wind and water and that eroded soil endangers aquatic flora and fauna and clogs drainage systems. Section 20-181 bars anyone from starting construction activity until the county engineer approves an erosion and sediment control plan, which must address applicable best management practices and keep a certified contractor on site whenever land-disturbing work occurs. Section 20-182 sets the technical standards: clearing cannot begin until sediment control devices are installed and stabilized; graded slopes and fills are capped at 4:1 or less, the angle vegetative cover or an approved erosion-control device can retain; slopes left exposed must be planted or otherwise stabilized within ten working days of completing any grading phase; cleared land sitting idle for more than 30 days needs ground cover within ten working days; and temporary seeding, sodding, or chemical stabilization is required on exposed soil, including stockpiles, whenever delays of more than seven days are expected.
Any project, or phase of a larger development, disturbing one acre or more must also keep a state Department of Environmental Protection stormwater permit on site for inspection. Waste generated on site, including concrete washout, chemicals, and building debris, must be stored or controlled to keep it out of the water. Section 20-183 exempts emergency work, MS4 maintenance and repair, permitted mining, and existing nursery or agricultural operations conducted as a permitted use, provided none of them cause erosion or degradation beyond the property line.
Violations & Fines
Erosion-control violations are enforced the same way as the rest of Article VI's stormwater program: the county engineer can issue a stop-work order and require remediation under section 20-145, and uncorrected violations move to code enforcement under chapter 1, article II, with the cost of any county-performed cleanup billed to the violator.
Frequently Asked Questions
Do I need a permit before clearing land in unincorporated St. Lucie County?
How steep can a graded slope be on a St. Lucie County construction site?
Are farms exempt from the county's erosion control rules?
Sources & Official References
Other rules in St. Lucie County
Florida rules heatmap·Compare St. Lucie County to another location·View the Florida environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.