Tangipahoa Parish, LA Environmental Rules: Erosion Control (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Governing law
Tangipahoa Parish Code § 36-111(h)(2)-(3)
SWPPP threshold
Required at 1 acre or more disturbed
LDEQ permit threshold
Required above 5 acres disturbed
Inspection frequency
Every 14 days and after 0.5-inch rain events
Noncompliance
48 hours to fix before stop-work order

Summary

Tangipahoa Parish requires a state-approved stormwater pollution prevention plan, or SWPPP, on any development disturbing an acre or more, rising to a full LDEQ discharge permit above five acres. The plan's best management practices must control sediment and erosion, stormwater retention and construction mitigation, and the parish inspects installed BMPs during construction under Section 36-111(h)(2) and (3).

These county ordinances apply to unincorporated areas of Tangipahoa Parish. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

a.Design of the SWPPP shall meet the latest requirements of the LDEQ. A SWPPP shall be developed and implemented for all developments disturbing one acre or greater. On developments over five acres a SWPPP shall be developed and a permit secured from LDEQ before implementing the SWPPP. ... b.BMPs required for sediment and erosion control, stormwater retention, and mitigation during construction.1.The contractor's use and description of the approved BMPs shall be included with their SWPPP.2.The contractor shall include all BMPs and provide verification of the SWPPP to the parish prior to construction.3.Installation of these BMPs may be inspected by the parish for proper maintenance during the project construction phase, unless the state inspects such activity as part of an approved SWPPP.

Full Breakdown

Section 36-111(h), 'Stormwater management and water quality,' requires every major subdivision, special use residential commercial development and general commercial development to include a stormwater pollution prevention plan, or SWPPP, under paragraph (2)(a). Paragraph (2)(b) specifically requires best management practices, or BMPs, for sediment and erosion control, stormwater retention and mitigation during construction, and it makes the contractor responsible for describing the approved BMPs in the SWPPP and verifying that description to the parish before construction begins. Paragraph (3) sets the size thresholds: a SWPPP must be developed and implemented for any development disturbing one acre or more, and a development over five acres must both develop a SWPPP and secure an LDEQ permit before implementing it, following the latest Louisiana Department of Environmental Quality standards.

Once construction starts, the contractor must keep the SWPPP documents on site and available to the parish engineer, floodplain administrator, drainage district administrator and LDEQ, and must inspect the installed BMPs every 14 days, before every anticipated storm, and within 24 hours of any half-inch rain event, documenting each inspection. Parish staff are authorized to inspect any development or building site for SWPPP violations under paragraph (3)(c); a noncompliant site gets a remediation plan and 48 hours to fix it before the parish engineer or building official can issue a written stop-work order.

Violations & Fines

A contractor who fails a follow-up inspection after a remediation plan receives a written notice of violation and a stop-work order from the parish engineer or the building official under Section 36-111(h)(3)(c). Violations are also subject to the fines and penalties in Section 1-13, and those fines continue to accrue until the parish issues a SWPPP notice of compliance; any fines must be paid before a resume-work order is issued.

Frequently Asked Questions

At what project size does Tangipahoa Parish require an erosion control plan?
Any development disturbing one acre or more must have a SWPPP under Section 36-111(h)(3)(a). Once the disturbed area exceeds five acres, the developer must also secure a discharge permit from the Louisiana Department of Environmental Quality before implementing that plan.
How often must erosion control measures be inspected during construction?
Section 36-111(h)(3)(a)(5) requires the contractor or its designee to inspect SWPPP best management practices every 14 days, before every anticipated storm event, and within 24 hours of any rain event of half an inch or more, with each inspection documented in the SWPPP file.
What happens if my construction site isn't following its erosion control plan?
The parish reports noncompliant conditions to your on-site representative and sets a remediation plan, giving you 48 hours to fix the violations under Section 36-111(h)(3)(c). If a follow-up inspection still finds violations, the parish engineer or building official issues a written stop-work order and Section 1-13 fines can accrue.

Sources & Official References

Other rules in Tangipahoa Parish

All Tangipahoa Parish rules

Compare Tangipahoa Parish to another location·View the Louisiana environmental rules overview

Get notified when Erosion Control in Tangipahoa Parish, LA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.