Tangipahoa Parish, LA Environmental Rules: Flood Elevation Requirements (2026)
Key Facts
- Freeboard required
- 12 inches above base flood elevation
- Applies to
- new construction and substantial improvements
- Certification by
- registered engineer, architect or land surveyor
- Small appurtenant structures
- under 550 sq ft need flood-equalizing openings, not elevation
- FIRM basis
- FEMA Flood Insurance Study dated July 22, 2010
- Max penalty
- $500.00 fine or 30 days jail per violation
Summary
New and substantially improved residential structures in Tangipahoa Parish flood hazard areas must have their lowest floor, including any basement, elevated at least 12 inches above the base flood elevation. An engineer, architect or land surveyor must certify compliance to the parish floodplain administrator before the permit is finalized.
Sec. 36-285. - Specific standards. In all areas of special flood hazard where base flood elevation data has been provided as set forth in section 36-243, 36-266(a)(8), or 36-286(c), the following provisions are required: ... (1)Residential construction. New construction and substantial improvement of any residential structure shall have the lowest floor (including basement) elevated to at least 12 inches above the base flood elevation.a.A registered professional engineer, architect, or land surveyor shall submit a certification to the floodplain administrator that the standard of this subsection, as proposed in section 36-266(a), is satisfied.
Full Breakdown
Parish Code section 36-285 sets the specific flood-hazard-reduction standards that apply once base flood elevation data has been established for a site under sections 36-243, 36-266(a)(8) or 36-286(c). For residential construction, the lowest floor, including a basement, must sit at least 12 inches above the base flood elevation (BFE), and a registered professional engineer, architect or land surveyor must certify that standard to the floodplain administrator. Nonresidential structures may instead be floodproofed watertight below the BFE if an engineer certifies the design. Standalone enclosed appurtenant structures under 550 square feet need hydrostatic flood-equalizing openings rather than full elevation, while those 550 square feet or larger must be elevated to the BFE plus the required freeboard like a primary structure.
In coastal high hazard zones (V, VE, V1-30), section 36-289 pushes the same 12-inch freeboard requirement onto pilings and columns, measured to the bottom of the lowest horizontal structural member, reflecting the added risk from hurricane wave action and tidal surge. Base flood elevation itself comes from the FEMA Flood Insurance Study and accompanying Flood Insurance Rate Maps for Tangipahoa Parish, dated July 22, 2010, and any later revisions, adopted by reference under section 36-243. The floodplain administrator, appointed by the parish president, reviews elevation certificates and can require additional engineering data when FIRM data is incomplete for a parcel. 00 in fines or 30 days in jail per violation, with each day of noncompliance counted separately, and violators also cover court costs.
Violations & Fines
Failing to elevate the lowest floor at least 12 inches above base flood elevation, or building without the required engineer or surveyor certification, is enforced as a violation of Article IX under section 36-249: a misdemeanor carrying a fine up to $500.00, up to 30 days imprisonment, or both, with each day of continuing noncompliance treated as a new offense.
Frequently Asked Questions
How high above base flood elevation must a house be built in Tangipahoa Parish?
Does the freeboard rule apply to sheds and detached garages?
What is base flood elevation based on in Tangipahoa Parish?
Sources & Official References
Other rules in Tangipahoa Parish
Compare Tangipahoa Parish to another location·View the Louisiana environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.