Trenton, NJ Environmental Rules: Erosion Control (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Governing local section
Trenton Code § 254-3
State standard incorporated
N.J.S.A. 4:24-39 et seq.
Implementing rules
N.J.A.C. 2:90
Applies to
Both major and minor development
Permit submission
Site plan under § 254-10 / § 315-20.2
Penalty for noncompliance
Up to $1,000, then $100/day

Summary

Trenton ties erosion control for major and minor development to the state Soil Erosion and Sediment Control Act (N.J.S.A. 4:24-39 et seq.) and N.J.A.C. 2:90, folding those minimum standards into Chapter 254's stormwater management review for every project subject to municipal approval.

Stormwater management measures for major development shall be designed to provide erosion control, groundwater recharge, stormwater runoff quantity control, and stormwater runoff quality treatment as follows: The minimum standards for erosion control are those established under the Soil and Sediment Control Act, N.J.S.A. 4:24-39 et seq., and implementing rules at N.J.A.C. 2:90. ... Stormwater management measures for minor development shall be designed to provide erosion control and stormwater runoff control, as follows: The minimum standards for erosion control are those established under the Soil and Sediment Control Act, N.J.S.A. 4:24-39 et seq., and implementing rules at N.J.A.C. 2:90.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: rev 4853025; v21 updated 2025-12-16; through 12-16-2025).

Full Breakdown

A. C. " Trenton does not write its own numeric erosion limits; it adopts the state act and its implementing rules as the floor for every development application. That requirement is carried into the permitting process at § 254-10, where the Site Development Stormwater Plan's environmental site analysis must identify areas particularly susceptible to erosion and sediment loss and address source controls like minimizing land disturbance, clearing, grading, and soil compaction, and must apply post-construction fertilizer only in accordance with the Soil Erosion and Sediment Control Act.

A. 4:24-39 as a required submission item for site plan and subdivision review. Chapter 254 itself defines EROSION as "the detachment and movement of soil or rock fragments by water, wind, ice, or gravity," underscoring that construction-phase soil loss, not just post-development runoff volume, is squarely within the article's design and performance standards for both major and minor projects.

Violations & Fines

Erosion control is enforced as part of Chapter 254, Article I, so a project built or maintained without meeting the Soil Erosion and Sediment Control Act standards incorporated at § 254-3 is subject to the same penalties as any other stormwater violation under § 254-11.1: a fine of up to $1,000 per violation, 30 days to correct the deficiency, and a continuing fine of up to $100 per day for each day the site remains out of compliance after that.

Frequently Asked Questions

Does Trenton have its own erosion control numbers?
No. Trenton Code § 254-3 sets erosion control for both major and minor development by reference: "the minimum standards for erosion control are those established under the Soil and Sediment Control Act, N.J.S.A. 4:24-39 et seq., and implementing rules at N.J.A.C. 2:90," so the state act's standards govern site work in the city.
What has to be submitted to show erosion control on a project?
Applicants submit a Site Development Stormwater Plan under § 254-10 with an environmental site analysis identifying erosion-susceptible areas and describing measures to minimize land disturbance, clearing, grading, and soil compaction; Chapter 315's checklist also requires a soil erosion and sediment control plan referencing N.J.S.A. 4:24-39.
Does erosion control apply to small residential projects?
Yes. Section 254-3(B) applies the same Soil Erosion and Sediment Control Act standard to minor development, not just major development, meaning erosion control is required regardless of project size.
What is the penalty for an uncontrolled erosion site in Trenton?
It falls under the Chapter 254, Article I penalty at § 254-11.1: up to $1,000 per violation, 30 days to correct, then up to $100 per day the site remains out of compliance.

Sources & Official References

Other rules in Trenton

All Trenton rules

Compare Trenton to another location·View the New Jersey environmental rules overview

Get notified when Erosion Control in Trenton, NJ changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.