Tustin, CA Environmental Rules: Erosion Control (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Erosion control plan trigger
>200 cu. yd. Oct. 15-Apr. 15 (§8923C)
Desilting basin compaction
90% relative density (§8923I)
Rainy season
Oct. 1-Apr. 30 (§8905)
Inspection required by
civil engineer each rainy season (§8923E)
Non-compliance remedy
permit revocation (§8924E)

Summary

The City of Tustin bars grading over 200 cubic yards on any site between October 15 and April 15 unless an erosion control system has been filed and approved under Tustin City Code Section 8923. Property owners must retain a civil engineer to inspect erosion and sediment control devices, and desilting basins must be compacted to 90 percent relative density.

A.The faces of cut and fill slopes and the project site shall be prepared and maintained to control against erosion. ... C.No grading work in excess of two hundred (200) cubic yards will be allowed between October 15th and April 15th on any single grading site under permit unless an erosion control system has been filed and approved or waived in writing by the Building Official. ... I.Desilting basins constructed of compacted earth shall be compacted to a relative compaction of ninety (90) percent of maximum density.

Full Breakdown

Tustin City Code Chapter 9 of Article 8 governs grading, and Section 8923 sets the City's erosion control and water quality requirements. Cut and fill slopes and the project site must be prepared and maintained against erosion, generally through effective planting installed as soon as practical and before final approval; drought-resistant and, in hillside areas, fire-retardant plants are recommended. No grading over 200 cubic yards may proceed on any single permitted site between October 15 and April 15 unless an erosion control system has been filed and approved, or waived in writing, by the Building Official.

Unless waived, the owner must retain a civil engineer to inspect and give initial approval of permanent and semi-permanent erosion and sediment control devices every rainy season (October 1 through April 30, per the Section 8905 definitions) and to revise the plan as field conditions require. Desilting facilities are required at every drainage outlet from a graded site, and desilting basins built of compacted earth must reach 90 percent relative compaction, verified by a soil engineering report submitted to the Building Official. During the rainy season, disturbed areas that are not actively being graded must be fully protected with best management practices, and standby erosion-control materials must be stored on site and ready to deploy within 48 hours of a forecast with a 50 percent chance of rain, even in the dry season.

Removable protective devices must be in place at the end of each working day whenever the five-day rain forecast exceeds a 40 percent chance, and slopes over five feet high need effective planting, with slopes over 15 feet potentially requiring irrigation.

Violations & Fines

Section 8924 makes the contractor, permittee, and property owner jointly responsible for maintaining every erosion and sediment control device; after each rainstorm, silt and debris must be cleared from basins and the system's performance evaluated and repaired. If maintenance is neglected, the Building Official may perform emergency work and bill the owner for mobilization plus the cost of the work, and may revoke the grading permit in writing; it will not be reinstated until an approved system is installed and any penalty fee is paid. Section 8923(Q) also makes any violation of a state or federal storm water permit a violation of this chapter.

Frequently Asked Questions

How much grading can I do without an erosion control plan?
Up to 200 cubic yards is allowed on a single site between October 15 and April 15 without a filed and approved erosion control system; beyond that, Tustin City Code Section 8923(C) requires the plan to be approved or waived in writing by the Building Official before work continues.
Who has to inspect my erosion control devices?
Unless the Building Official waives it, the property owner must retain a civil engineer to give initial approval of the erosion and sediment control system and to periodically review field conditions throughout the rainy season under Section 8923(E).
What happens if I don't maintain my desilting basin?
The Building Official can perform emergency maintenance and charge the owner for mobilization and labor, and can revoke the grading permit in writing until an approved erosion and sediment control system is installed and any penalty fee is paid, per Section 8924.

Sources & Official References

Other rules in Tustin

All Tustin rules

California rules heatmap·Compare Tustin to another location·View the California environmental rules overview

Get notified when Erosion Control in Tustin, CA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Erosion Control in Nearby Cities

How other cities in Orange County handle erosion control.

Santa Ana, CA
Some Restrictions
Fullerton, CA
Some Restrictions
Huntington Beach, CA
Some Restrictions
Orange, CA
Some Restrictions
Newport Beach, CA
Some Restrictions
Mission Viejo, CA
Some Restrictions
Costa Mesa, CA
Some Restrictions
Anaheim, CA
Some Restrictions