Fresno County Code Chapter 15.28
State code adopted
2022 CBC/CRC Chapters 18, 33 and Appendix J
Trigger
Final inspection withheld until erosion control complete
Enforcing official
County Grading Official
Cross-effect
Building permit final approval waits on grading closeout

Summary

Fresno County requires every grading permit to complete erosion-control measures before the county will approve final inspection. Chapter 15.28 adopts the California Building Code's Appendix J grading standards, amended locally so that drainage facilities, protective devices and erosion control must all be finished and verified before the Grading Official closes out the permit.

City-specific rules exist: Clovis, and Fresno have their own erosion control rules that differ from Fresno County's county-level regulations. If you live in one of those cities, check the city-specific page instead.

The permittee shall notify the Grading Official when the grading operation is ready for Final Inspection. Final approval shall not be given until all work, including installation of all drainage facilities and their protective devices, and all erosion-control measures have been completed in accordance with the final approved Grading Plan, and the required reports have been submitted.

If an owner or contractor completes his portion of the work described when the Grading Permit was issued, he may request a Completion Notice for this portion of work prior to the Final Completion Notice or the expiration of the Grading Permit.

9.Concurrent Permits. Any grading work which is done in preparation for a structure, must obtain final approval of the Grading Permit prior to final approval of the corresponding Building Permit unless other provisions have been made.

V.Appendix J, Section J111 and Chapter 35 Referenced Standards is amended to add the following referenced standards: ASTM D 1556, In Place Density of Soils by the Sand-Cone

ASTM D 2167, In Place Density of Soils by the Rubber-Balloon Method

ASTM D 2922 In Place Density of Soil by Nuclear Methods (Shallow Depth)

ASTM D 2937, In Place Density of Soils by the Drive-Cylinder Method.

ASTM D 2922 and D 3017, In Place Moisture Contact and Density of Soils by Nuclear Methods.

ASTM D 3017, In Place Water Content of Soil by Nuclear Methods (Shallow Depth).

Source: Fresno County Grading Ordinance Title 14View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 51).

Full Breakdown

020 rewrites several of those state provisions with county-specific amendments. U, spells out the completion sequence: the permittee has to notify the Grading Official when the grading operation is ready for final inspection, and the county withholds final approval until all work, including installation of every drainage facility and its protective devices, and all erosion-control measures, has been completed in accordance with the approved Grading Plan and the required geotechnical reports have been submitted. The same amended section requires professional inspection during the work itself: a retained Soils Engineer has to observe grading and compaction testing, and a Civil Engineer and Engineering Geologist cover their own technical specialties, with any discrepancy from the approved plan reported immediately in writing to both the permittee and the Grading Official.

If the engineer of record changes mid-project, grading stops until the replacement accepts responsibility in writing. Concurrent building permits cannot receive final approval until the corresponding grading permit closes out first, which ties erosion-control completion directly to a project's ability to finish construction. These amendments were most recently carried forward by Ordinance No. 23-001 on February 28, 2023.

Violations & Fines

A grading operation that has not finished its erosion-control measures, drainage facilities and protective devices cannot pass final inspection. The Grading Official can refuse to issue the Notice of Completion, which in turn blocks final approval of any related building permit, and can require the permittee, Civil Engineer or Soils Engineer to submit revised plans before work proceeds further.

Frequently Asked Questions

When does Fresno County require erosion control to be finished?
Before final inspection of a grading permit. Fresno County Code Section 15.28.020 amends CBC Appendix J to state that final approval will not be given until all work, including drainage facilities and their protective devices and all erosion-control measures, has been completed according to the approved Grading Plan and the required reports have been submitted to the Grading Official.
Who checks that erosion control was actually installed?
The Grading Official conducts the final inspection, but the permit also requires professional oversight during the work itself: a retained Soils Engineer observes compaction and grading, and a Civil Engineer and Engineering Geologist review conditions within their specialties. Any discrepancy between field conditions and the approved plan has to be reported in writing to the permittee and the Grading Official right away.
Can I get my building permit finaled before the grading permit is done?
No. Fresno County Code Section 15.28.020.U states that grading work performed in preparation for a structure has to obtain final approval of the Grading Permit before final approval of the corresponding Building Permit, unless the county has made other arrangements in writing.

Sources & Official References

Other rules in Fresno County

All Fresno County rules

California rules heatmap·Compare Fresno County to another location·View the California environmental rules overview

Get notified when Erosion Control in Fresno County, CA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Erosion Control in Cities Across Fresno County