Clovis, CA Environmental Rules: Erosion Control (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified August 2026

Key Facts

Governing section
Clovis Municipal Code § 9.110.040(A)(4), (A)(8), (B)
Plan preparer
Registered civil engineer
Approving official
City Engineer
Reference standard
CBC Appendix Chapter 70
Security
Bond required before grading on unrecorded parcels

Summary

Clovis Municipal Code Section 9.110.040 requires every subdivision grading plan to use best-available management practices to hold down erosion, sedimentation, and dust, and to be designed with erosion and sediment control measures built in. Final maps are conditioned on compliance with the erosion-control provisions of Appendix Chapter 70 of the California Building Code.

4. Grading practices. All grading within the City shall employ the best available management practices, as determined by the City Engineer, to minimize erosion, sedimentation, airborne dust, and unnecessary grading. Each building site on sloping parcels shall be individually prepared... 8. Compliance with California Building Code required. Every map approved in compliance with the provisions of this chapter shall be conditioned on compliance with the requirements for grading and erosion control, including the prevention of sedimentation or damages to off-site property, in compliance with Appendix Chapter 70 of the California Building Code, as adopted and amended from time to time by the City... B. Erosion and sediment control. A proposed subdivision shall be designed so that all grading incorporates appropriate erosion and sediment control measures.

Full Breakdown

040 sets the grading standards a subdivider must meet before the City issues a building permit for a new subdivision in Clovis. Subsection A requires a grading plan prepared and signed by a registered civil engineer, submitted to and approved by the City Engineer, showing natural and finished grades, pad and floor elevations, drainage swale directions, retaining wall heights, and existing topography and drainage outside the project boundary. 3 bars inter-parcel 'cross drainage,' requiring each parcel to drain to a public street or an approved drainage facility rather than across a neighboring lot.

4, Grading practices, requires all grading citywide to employ the best available management practices, as determined by the City Engineer, specifically to minimize erosion, sedimentation, airborne dust, and unnecessary grading, with each building site on a sloping parcel individually prepared. 6 lets the City require a bond before grading begins on a site not yet recorded, to cover landscaping and erosion control if the subdivider abandons the project mid-grade. 8 conditions every approved subdivision map on compliance with the grading and erosion-control requirements, including prevention of sedimentation or damage to off-site property, found in Appendix Chapter 70 of the California Building Code. 070 must recommend corrective action and special erosion-control precautions.

Violations & Fines

A subdivision map or grading plan that does not incorporate the required erosion and sediment control measures, or that fails to follow Appendix Chapter 70 of the California Building Code, is not entitled to final map approval; the City Engineer can withhold grading approval, and if a subdivider abandons a site after grading without completing erosion control, the City can draw on the Section A.6 bond to install the required landscaping and erosion measures itself.

Frequently Asked Questions

Does a Clovis subdivision need erosion control during grading?
Yes. Section 9.110.040(B) requires every proposed subdivision to be designed so that its grading incorporates appropriate erosion and sediment control measures, and subsection (A)(4) separately requires the best available management practices to minimize erosion, sedimentation, and dust citywide.
Who approves a subdivision grading plan in Clovis?
The City Engineer. Section 9.110.040(A) requires a grading plan prepared and signed by a registered civil engineer, submitted to and approved by the City Engineer before a building permit is issued for the subdivision.
What happens if a developer abandons a Clovis subdivision after grading starts?
Section 9.110.040(A)(6) lets the City require a bond before grading on an unrecorded parcel, which the City can use to install landscaping and erosion control measures if the subdivider walks away mid-project.

Sources & Official References

Other rules in Clovis

All Clovis rules

California rules heatmap·Compare Clovis to another location·View the California environmental rules overview

Get notified when Erosion Control in Clovis, CA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Erosion Control in Nearby Cities

How other cities in Fresno County handle erosion control.

Fresno, CA
Some Restrictions