Clovis, CA Environmental Rules: Flood Elevation Requirements (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified August 2026

Key Facts

Governing section
Clovis Municipal Code § 8.12.05(a)(3)
Residential standard
Lowest floor per CRC/CBC elevation
Nonresidential option
Dry floodproofing with engineer certification
Flood vent ratio
1 sq in per sq ft of enclosed area
Manufactured homes
Chassis min. 36 inches above grade

Summary

In a Clovis special flood hazard area, Municipal Code Section 8.12.05(a)(3) ties the required lowest-floor elevation to whichever standard applies under the California Residential Code or California Building Code, rather than setting its own number. Nonresidential buildings may floodproof instead of elevate, but only with an engineer's or architect's certification.

(3) Elevation and floodproofing. i. Residential construction. All new construction or substantial improvements of residential structures shall have the minimum elevation of lowest floor, including basement, built to the level specified by the California Residential Code or the California Building Code. ii. Nonresidential construction. All new construction or substantial improvements of nonresidential structures shall either be elevated to conform with subsection (a)(3)(i) of this section or: a. Be floodproofed, together with attendant utility and sanitary facilities, below the elevation recommended under subsection (a)(3)(i) of this section, so that the structure is watertight with walls substantially impermeable to the passage of water; b. Have structural components capable of resisting hydrostatic and hydrodynamic loads and effects of buoyancy; and c. Be certified by a registered civil engineer or architect that the standards of subsections (a)(3)(ii)(a) and (b) of this section are satisfied.

Full Breakdown

05(a) sets the construction standards that apply to all new buildings and substantial improvements within a mapped special flood hazard area in Clovis. 02(j) as the elevation of the one-percent-annual-chance flood plus wave height, relative to the applicable federal or state datum shown on the Flood Insurance Rate Map. Nonresidential buildings get an alternative under subsection (a)(3)(ii): instead of elevating to the residential standard, they may be dry-floodproofed below that elevation so the structure and its utilities and sanitary facilities stay watertight, with structural components engineered to resist hydrostatic and hydrodynamic loads and the effects of buoyancy, but only if a registered civil engineer or architect certifies the standard is met and files that certification with the Floodplain Administrator.

Subsection (a)(3)(iii) separately requires enclosed areas below the lowest floor used for parking, access, or storage to have flood openings, at least two on different walls, sized to at least one square inch per square foot of enclosed area, with the lowest opening no higher than one foot above grade. Manufactured homes get their own elevation rule under subsection (d): the lowest floor must reach the CBC/CRC elevation, or the chassis must sit on reinforced piers at least 36 inches above grade in an existing park.

Violations & Fines

Elevation and floodproofing failures fall under the same misdemeanor enforcement as the rest of Chapter 8.12 (Section 8.12.03(c)): building below the required lowest-floor elevation, or floodproofing a nonresidential structure without the required engineer's or architect's certification on file with the Floodplain Administrator, is a violation subject to City enforcement action, and the City may take any lawful action necessary to prevent or remedy it.

Frequently Asked Questions

How high above the flood level must my Clovis house be built?
Section 8.12.05(a)(3)(i) requires the lowest floor, including any basement, of a new or substantially improved residential structure in a special flood hazard area to be built to the elevation set by the California Residential Code or California Building Code for that site's base flood elevation.
Can a commercial building in a Clovis flood zone skip elevating and floodproof instead?
Yes, under Section 8.12.05(a)(3)(ii), but only if a registered civil engineer or architect certifies the structure is watertight below the required elevation and its components can resist hydrostatic and hydrodynamic loads, with that certification filed with the Floodplain Administrator.
Do garages in a Clovis flood zone need vents or openings?
Yes. Section 8.12.05(a)(3)(iii) requires enclosed areas below the lowest floor used for parking or storage to have at least two flood openings on different walls totaling one square inch per square foot of enclosed area, with the lowest opening no more than one foot above grade.

Sources & Official References

Other rules in Clovis

All Clovis rules

California rules heatmap·Compare Clovis to another location·View the California environmental rules overview

Get notified when Flood Elevation Requirements in Clovis, CA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Flood Elevation Requirements in Nearby Cities

How other cities in Fresno County handle flood elevation requirements.

Fresno, CA
Some Restrictions