Bolingbrook, IL Environmental Rules: Flood Elevation Requirements (2026)
Key Facts
- Minimum freeboard, basins
- 1 foot above 100-yr water level
- Minimum freeboard, culverts/bridges
- 1 foot at upstream face
- Compensatory storage, flood fringe
- 1.5x volume displaced
- Base flood elevation defined
- 100-year frequency flood level
- Penalty
- $200-$1,000 per day
- Mapped regulatory floodways
- Lily Cache Creek, DuPage River, tributaries
Summary
Detention basins built under Bolingbrook's stormwater rules must keep at least one foot of freeboard between the 100-year flood water level and the top of the embankment, and new roadway culverts crossing streams need the same one-foot freeboard at the upstream face. A detention basin placed in a flood fringe area must replace 1.5 times the storage volume it displaces below the 100-year base flood elevation.
Freeboard. ... Minimum freeboard between the 100-year event water level and top of embankment shall be one foot. ... Freeboard between the 100-year water surface elevation and the low chord of proposed culverts or bridges shall not be less than one foot at the upstream face. ... The placement of a detention basin in a flood fringe area shall require compensatory storage for 1.5 times the volume below the 100-year base flood elevation occupied by the detention basin, including any berms.
Full Breakdown
The freeboard and base flood elevation standards sit in the same stormwater management division as the village's drainage rules, Chapter 16, Article IV, Division 2. Section 16-115 defines base flood elevation as the elevation delineating the level of flooding from the 100-year frequency flood event, and defines freeboard as the added height above the 100-year high water elevation built in to cover uncertainties in calculations, unknown local conditions, wave action and debris jams. Section 16-120(f)(6) sets that freeboard at a minimum of one foot between the 100-year event water level and the top of embankment for wet detention basins, and Section 16-120(g)(4) applies the same one-foot minimum to dry detention basins between the 100-year high water level and the top of embankment.
Section 16-120(l)(3) extends the one-foot freeboard standard to culvert and bridge crossings, measured between the 100-year water surface elevation and the low chord of the structure at its upstream face. 5 times the volume displaced below the 100-year base flood elevation, replacing floodwater storage lost below the ten-year flood elevation with storage below the ten-year elevation and storage lost above it with storage above the proposed ten-year elevation. The village's regulatory floodways, mapped by FEMA, cover Lily Cache Creek, the Lily Cache Lane Tributary, the Naperville Road Tributary and the DuPage River.
Violations & Fines
Building a detention basin, culvert or crossing without the required one-foot freeboard, or filling flood fringe storage without providing the 1.5-to-1 compensatory volume, violates the stormwater division under Section 16-134. The village can fine the responsible party $200.00 to $1,000.00 per violation, and every day the shortfall in freeboard or storage continues counts as a new offense.
Frequently Asked Questions
How much freeboard does Bolingbrook require on a detention basin?
What freeboard applies to a culvert or bridge over a stream?
Can I fill part of the floodplain to build a detention pond?
What is Bolingbrook's base flood elevation?
Sources & Official References
Other rules in Bolingbrook
Compare Bolingbrook to another location·View the Illinois environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.
Flood Elevation Requirements in Nearby Cities
How other cities in Will County handle flood elevation requirements.