Brentwood, CA Environmental Rules: Flood Elevation Requirements (2026)
Key Facts
- A-zone freeboard
- 1 foot above base flood elevation
- All other zones freeboard
- 2 feet above base flood elevation
- AO-zone default
- 4 feet above highest adjacent grade
- Certification required
- registered engineer or surveyor
- Flood vent opening ratio
- 1 sq in per sq ft enclosed
Summary
Brentwood requires new and substantially improved residential structures in flood hazard areas to elevate the lowest floor one foot above base flood elevation in A zones, or two feet above it in every other flood zone.
1. Residential construction, new or substantial improvement, shall have the lowest floor, including basement: a. In an AO zone, elevated above the highest adjacent grade to a height equal to or exceeding the depth number specified in feet on the FIRM, or elevated at least four feet above the highest adjacent grade if no depth number is specified; b. In an A zone, elevated to one foot above the base flood elevation; said base flood elevation shall be determined by one of the methods in Section 15.07.220(b) of this chapter; c. In all other zones, elevated to two feet above the base flood elevation.
Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: rev 4604307; v5 updated 2025-12-09).
Full Breakdown
300(C), part of the city's floodplain management chapter, sets construction elevation standards for all areas of special flood hazard. For AO zones, the lowest floor including any basement must be elevated above the highest adjacent grade to a height equal to or exceeding the depth number shown on the Flood Insurance Rate Map, or at least four feet above the highest adjacent grade if no depth number is specified. 220(b). For every other flood zone, the freeboard requirement doubles: the lowest floor must be elevated to two feet above the base flood elevation.
Once built, a registered professional engineer or surveyor must certify the lowest floor's elevation, and the city's community building inspector must verify it before that certification goes to the floodplain administrator. Nonresidential construction can instead be flood-proofed watertight below the same elevation, with structural components certified to resist hydrostatic and hydrodynamic loads. Enclosed areas below the lowest floor used only for parking, access or storage must have flood vents sized to at least one square inch of opening per square foot of enclosed area, with the bottom of openings no higher than one foot above grade, so floodwater can enter and exit automatically rather than pushing on the walls.
Violations & Fines
Construction that fails to meet the elevation or flood-proofing certification requirements of Section 15.07.300 is enforced by the city's floodplain administrator, who reviews the required engineer or surveyor elevation certification before accepting a project as compliant; a structure lacking that certification or built below the required freeboard is treated as noncompliant with the floodplain management chapter, subject to the chapter's general permit and appeal provisions under Sections 15.07.200 and 15.07.230.
Frequently Asked Questions
How high above base flood elevation must a new Brentwood home be built?
Who certifies that a Brentwood building meets the flood elevation requirement?
Can a garage below the required flood elevation be enclosed in Brentwood?
Sources & Official References
Other rules in Brentwood
California rules heatmap·Compare Brentwood to another location·View the California environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.
Flood Elevation Requirements in Nearby Cities
How other cities in Contra Costa County handle flood elevation requirements.