Brentwood, CA Environmental Rules: Flood Elevation Requirements (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

A-zone freeboard
1 foot above base flood elevation
All other zones freeboard
2 feet above base flood elevation
AO-zone default
4 feet above highest adjacent grade
Certification required
registered engineer or surveyor
Flood vent opening ratio
1 sq in per sq ft enclosed

Summary

Brentwood requires new and substantially improved residential structures in flood hazard areas to elevate the lowest floor one foot above base flood elevation in A zones, or two feet above it in every other flood zone.

1. Residential construction, new or substantial improvement, shall have the lowest floor, including basement: a. In an AO zone, elevated above the highest adjacent grade to a height equal to or exceeding the depth number specified in feet on the FIRM, or elevated at least four feet above the highest adjacent grade if no depth number is specified; b. In an A zone, elevated to one foot above the base flood elevation; said base flood elevation shall be determined by one of the methods in Section 15.07.220(b) of this chapter; c. In all other zones, elevated to two feet above the base flood elevation.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: rev 4604307; v5 updated 2025-12-09).

Full Breakdown

300(C), part of the city's floodplain management chapter, sets construction elevation standards for all areas of special flood hazard. For AO zones, the lowest floor including any basement must be elevated above the highest adjacent grade to a height equal to or exceeding the depth number shown on the Flood Insurance Rate Map, or at least four feet above the highest adjacent grade if no depth number is specified. 220(b). For every other flood zone, the freeboard requirement doubles: the lowest floor must be elevated to two feet above the base flood elevation.

Once built, a registered professional engineer or surveyor must certify the lowest floor's elevation, and the city's community building inspector must verify it before that certification goes to the floodplain administrator. Nonresidential construction can instead be flood-proofed watertight below the same elevation, with structural components certified to resist hydrostatic and hydrodynamic loads. Enclosed areas below the lowest floor used only for parking, access or storage must have flood vents sized to at least one square inch of opening per square foot of enclosed area, with the bottom of openings no higher than one foot above grade, so floodwater can enter and exit automatically rather than pushing on the walls.

Violations & Fines

Construction that fails to meet the elevation or flood-proofing certification requirements of Section 15.07.300 is enforced by the city's floodplain administrator, who reviews the required engineer or surveyor elevation certification before accepting a project as compliant; a structure lacking that certification or built below the required freeboard is treated as noncompliant with the floodplain management chapter, subject to the chapter's general permit and appeal provisions under Sections 15.07.200 and 15.07.230.

Frequently Asked Questions

How high above base flood elevation must a new Brentwood home be built?
It depends on the flood zone. Section 15.07.300(C)(1) requires one foot of freeboard above base flood elevation in an A zone, but two feet of freeboard in every other special flood hazard zone besides AO, where a different grade-based standard applies.
Who certifies that a Brentwood building meets the flood elevation requirement?
A registered professional engineer or surveyor must certify the elevation of the lowest floor once construction is complete, and the community building inspector verifies it before the certification is submitted to the city's floodplain administrator under Section 15.07.300(C)(1).
Can a garage below the required flood elevation be enclosed in Brentwood?
Yes, but Section 15.07.300(C)(3) requires flood vents allowing floodwater to enter and exit automatically: at least one square inch of opening per square foot of enclosed area, with openings no higher than one foot above grade, unless a registered engineer or architect certifies an alternative design.

Sources & Official References

Other rules in Brentwood

All Brentwood rules

California rules heatmap·Compare Brentwood to another location·View the California environmental rules overview

Get notified when Flood Elevation Requirements in Brentwood, CA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.