Minimum freeboard
1 foot above base flood data
Critical facility (Class IV) freeboard
2 feet above 500-year/FHACA elevation
Critical facility (Class III) freeboard
1 foot in coastal high-hazard areas
Zone AO default
3 feet above highest adjacent grade
Adopted by
Ordinance No. 2023-6, July 10, 2023
Enforcing officer
Floodplain Administrator

Summary

Cherry Hill Township sets a Local Design Flood Elevation (LDFE) above the mapped or state flood elevation for new construction and substantial improvements, adding at least one foot of freeboard, with two feet required for Class IV critical facilities under § 12-102.3.

At a minimum, the Local Design Flood Elevation shall be as follows: 1. For a delineated watercourse, the elevation associated with the Best Available Flood Hazard Data Area determined in § 12-102.2, above plus one foot or as described by N.J.A.C. 7:13 of freeboard... 4. ... Class IV Critical Facilities. For any proposed development of new and substantially improved Flood Design Class IV Critical Facilities, the Local Design Flood Elevation must be the higher of the 0.2% annual chance (500-year) flood elevation or the Flood Hazard Area Design Flood Elevation with an additional two feet of freeboard in accordance with ASCE 24.

Full Breakdown

Section 12-102.3, added by Ordinance No. 2023-6 on July 10, 2023, establishes the Local Design Flood Elevation using the best available flood hazard data described in § 12-102.2, the Flood Hazard Area Control Act's minimum statewide elevation requirements for A, Coastal A and V zones, and ASCE 24 requirements for critical facilities, plus additional freeboard set by the chapter. For a delineated watercourse, the LDFE is the elevation from the Best Available Flood Hazard Data Area plus one foot, or the freeboard described by N.J.A.C.

7:13, whichever applies. For an undelineated watercourse with 50 or more acres of contributory drainage, applicants must submit either an unexpired NJDEP Flood Hazard Area Verification plus one foot of freeboard and any additional ASCE 24 freeboard, or a Method 5 or Method 6 determination under N.J.A.C. 7:13 plus one foot of freeboard and any additional ASCE 24 freeboard, sealed and submitted under §§ 12-105.2 and 12-105.3. In Zone AO areas, the LDFE is the highest adjacent grade plus the FIRM panel's depth number plus one foot of freeboard, or three feet above the highest adjacent grade if no depth number is specified.

New or substantially improved Flood Design Class IV critical facilities must be built to the higher of the 0.2%-annual-chance (500-year) flood elevation or the Flood Hazard Area Design Flood Elevation plus two feet of freeboard under ASCE 24, and Class III critical facilities in coastal high-hazard areas get the same 500-year/FHACA comparison plus one foot of freeboard. The Floodplain Administrator in the Department of Community Development enforces these elevation standards alongside the Construction Official, who administers the flood provisions of the Uniform Construction Code, N.J.A.C. 5:23, under § 12-103.3.

Violations & Fines

Constructing below the required Local Design Flood Elevation violates Chapter 12 and N.J.S.A. 40:49-5, exposing the property owner to a fine of not more than $1,250, imprisonment up to 90 days, or up to 90 days of community service, with each day of the deficiency treated as a separate violation. A repeat offense within one year adds a further court-set fine on top of the base penalty.

Frequently Asked Questions

How much freeboard does Cherry Hill Township require above base flood elevation?
Section 12-102.3 requires at least one foot of freeboard above the Best Available Flood Hazard Data Area elevation for a delineated watercourse, or the freeboard set by the state Flood Hazard Area Control Act, N.J.A.C. 7:13, whichever governs the site.
Does Cherry Hill require extra freeboard for critical facilities?
Yes. Under § 12-102.3.4, new or substantially improved Class IV critical facilities need two feet of additional freeboard above the higher of the 500-year flood elevation or the Flood Hazard Area Design Flood Elevation, per ASCE 24.
What elevation applies in a Zone AO area in Cherry Hill?
Section 12-102.3.3 sets the Local Design Flood Elevation at the highest adjacent grade plus the FIRM panel's depth number plus one foot of freeboard, or three feet above the highest adjacent grade if the panel lists no depth number.
Who determines the Local Design Flood Elevation for a Cherry Hill property?
The Floodplain Administrator in the Department of Community Development applies § 12-102.3 using FEMA mapping and, where relevant, an NJDEP Flood Hazard Area Verification or a Method 5/6 determination submitted under §§ 12-105.2 and 12-105.3.

Sources & Official References

Other rules in Cherry Hill

All Cherry Hill rules

Compare Cherry Hill to another location·View the New Jersey environmental rules overview

Get notified when Flood Elevation Requirements in Cherry Hill, NJ changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.