Decatur, AL Environmental Rules: Flood Elevation Requirements (2026)

Significant Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Freeboard
One foot above base flood elevation
Applies to
New construction and substantial improvements in A, AE, AH zones
Floodproofing
Non-residential only, watertight to one foot above BFE
Fill top elevation
No lower than one foot above BFE
Certificate
FEMA elevation certificate before certificate of occupancy
Penalty
Misdemeanor, fine up to $500, up to six months

Summary

In the City of Decatur, Alabama, City Code § 25-32(b)1 requires the lowest floor, including the basement, of new construction and substantial improvements in A, AE and AH flood zones to be elevated no lower than one foot above the base flood elevation, which the code calls the design flood elevation. Non-residential buildings can be dry floodproofed to the same level.

(b)Specific technical standards. In all special flood hazard areas designated as A, AE, AH (with engineered or estimated BFE), the following provisions are required:1.Residential and non-residential structures. Where BFE data is available, new construction, reconstruction or repairs made to a repetitive loss structure, and substantial improvement of any structure or manufactured home shall have the lowest floor, including basement, elevated no lower than one (1) foot above the base flood elevation (also referred to as the design flood elevation - DFE). Should solid foundation perimeter walls be used to elevate a structure, openings sufficient to facilitate the unimpeded movements of flood waters shall be provided in accordance with standards of section 25-32(b)3.

Full Breakdown

Decatur builds one foot of freeboard into its standard. Where base flood elevation (BFE) data is available, new construction, reconstruction or repairs made to a repetitive loss structure, and substantial improvement of any structure or manufactured home must have the lowest floor, including basement, elevated no lower than one foot above the BFE, also called the design flood elevation (DFE). When solid foundation perimeter walls are used, flood openings must be provided under § 25-32(b)3: at least two openings per enclosed area, a total net area of not less than one square inch per square foot of enclosed area, in at least two walls, with the bottom of each opening no higher than one foot above grade.

Non-residential structures in AE or AH zones can be dry floodproofed instead of elevated, but must be watertight to at least one foot above the BFE and certified by an Alabama licensed engineer or architect to ASCE 24 standards. Manufactured homes must sit with the lowest floor one foot or more above the BFE. Mechanical, electrical and plumbing devices in an enclosure go not less than one foot above the BFE. Structural fill must have a top no lower than one foot above the BFE and the nearest wall must be set back 25 feet from the floodplain boundary. Storage of hazardous substances in residential structures must be two feet above the BFE.

The permit process tracks the number. Plot plans show the regulatory lowest floor elevation, an as-built elevation certificate is due once the lowest floor is complete, and a FEMA elevation certificate (Form 81-31 or equivalent) must be filed before a certificate of occupancy. Under § 25-31(b)1.l, a lot removed from the SFHA by a LOMR-F must still meet the community's freeboard elevation.

Violations & Fines

Failure to submit the elevation certification or to correct deficiencies is cause for a notice of violation, a stop-work order, or withholding of the certificate of occupancy. Under § 25-30(h), a violation is a misdemeanor with a fine up to $500.00, up to six months in jail, or both, and each day after the notice counts as a separate offense. A Section 1316 declaration can end flood insurance on a noncompliant structure.

Frequently Asked Questions

How high must the first floor be above the flood level in Decatur?
Section 25-32(b)1 requires the lowest floor, including the basement, to be elevated no lower than one foot above the base flood elevation where BFE data is available. The code calls that height the design flood elevation.
Can a commercial building in Decatur floodproof instead of elevating?
Yes, but only non-residential structures in AE or AH zones. The building must be designed watertight to at least one foot above the base flood elevation, with impermeable walls, and an Alabama licensed engineer or architect must certify the design to ASCE 24 or a compatible standard.
Do I need an elevation certificate in Decatur?
Yes. Section 25-31(b) requires an as-built certification of the lowest floor elevation after it is completed, and a FEMA elevation certificate (Form 81-31 or equivalent) before a certificate of occupancy issues. Work started without the certifications is at the permit holder's risk.
Does removing land from the flood zone with fill end the freeboard rule?
No. Under § 25-31(b)1.l, on a lot removed from the special flood hazard area by a LOMR-F, the top of fill must meet the community's freeboard elevation. If it is lower, new structures, additions and substantial improvements still have to meet the required freeboard.

Sources & Official References

Other rules in Decatur

All Decatur rules

Compare Decatur to another location·View the Alabama environmental rules overview

Get notified when Flood Elevation Requirements in Decatur, AL changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.