Key Facts

Governing section
Jacksonville Beach Code § 34-772
Fallback base flood elevation
Three feet above highest adjacent grade
Zone AO design flood elevation
Highest adjacent grade plus mapped depth number
Zone AO default depth
Two feet where the map prints no depth
Elevation certificate preparer
Florida licensed professional surveyor
Elevated manufactured home piers
Not less than thirty-six inches above grade

Summary

In Jacksonville Beach, section 34-772 sets the fallback when a mapped flood area has no base flood elevation: the floodplain administrator can require engineered data or specify a base flood elevation three feet above the highest adjacent grade. In Zone AO, the design flood elevation is highest adjacent grade plus the mapped depth, or two feet if none is printed.

b. Information in flood hazard areas without base flood elevations (approximate Zone A). Where flood hazard areas are delineated on the FIRM and base flood elevation data have not been provided, the floodplain administrator shall: ... ii. ... Specify that the base flood elevation is three (3) feet above the highest adjacent grade at the location of the development, provided there is no evidence indicating flood depths have been or may be greater than three (3) feet. ... Design flood elevation. ... The elevation of the "design flood," including wave height, relative to the datum specified on the community's legally designated flood hazard map. In areas designated as Zone AO, the design flood elevation shall be the elevation of the highest existing grade of the building's perimeter plus the depth number (in feet) specified on the flood hazard map. In areas designated as Zone AO where the depth number is not specified on the map, the depth number shall be taken as being equal to two (2) feet.

View official code

Official source re-checked November 3, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 60).

Full Breakdown

Where a flood hazard area is delineated on the FIRM but no base flood elevation has been provided (approximate Zone A), section 34-772(a)(5)b directs the floodplain administrator to require the applicant to include base flood elevation data prepared under currently accepted engineering practices, or to obtain and provide data available from a federal or state agency or other source. If no such data exist, the available data do not reasonably reflect flooding conditions, or the data are known to be scientifically or technically incorrect, the administrator can specify that the base flood elevation is three feet above the highest adjacent grade at the development location, provided there is no evidence that flood depths have been or may be greater than three feet. Where the data will support a letter of map change from FEMA, the analyses must be prepared by a Florida licensed engineer or professional surveyor in the format FEMA requires, and the applicant pays the processing fees.

The design flood elevation includes wave height and is measured against the datum on the community's legally designated flood hazard map. In Zone AO it equals the elevation of the highest existing grade of the building perimeter plus the depth number in feet printed on the flood hazard map. If the map prints no depth number for a Zone AO area, the depth number is taken as two feet.

For buildings and structures exempt from the Florida Building Code, the owner must submit the lowest-floor elevation proof. After the lowest floor is placed and before further vertical construction, a certification of elevation sealed by a Florida licensed professional surveyor goes to the floodplain administrator, or, where the three-foot fallback set the elevation, the owner's own documentation of the lowest floor height above the highest adjacent grade. A final certification is due at final inspection. Elevated above-ground tanks must sit at or above the design flood elevation on a supporting structure, and a manufactured home on a pier foundation must have its frame supported by piers not less than thirty-six inches above grade, or meet the Florida Building Code, Residential Section R322.2 or R322.3.

Violations & Fines

A building or structure without the documentation of the lowest floor elevation, other required design certifications, or other evidence of compliance is presumed to be a violation until that documentation is provided. For development outside the Florida Building Code, the floodplain administrator can serve notices of violation or stop work orders on the owner, the owner's agent, or the person doing the work. Continuing work after service, other than work directed to remedy the violation, brings penalties as prescribed by law.

Frequently Asked Questions

What if my lot is in a flood area with no base flood elevation?
The floodplain administrator can require you to supply base flood elevation data prepared under accepted engineering practices, or use data from a federal or state agency. If nothing adequate exists, the administrator can specify a base flood elevation three feet above the highest adjacent grade at your site, absent evidence that depths are greater.
How is design flood elevation figured in Zone AO?
In Zone AO the design flood elevation is the elevation of the highest existing grade of the building perimeter plus the depth number, in feet, shown on the flood hazard map. Where the map does not specify a depth number for the Zone AO area, the code takes the depth number as two feet.
Who certifies the lowest floor elevation?
For buildings exempt from the Florida Building Code, a certification of elevation of the lowest floor prepared and sealed by a Florida licensed professional surveyor goes to the floodplain administrator after the lowest floor is placed. If the three-foot fallback set the elevation, the owner or agent supplies the height documentation instead.
Does section 34-772 print a freeboard figure for buildings?
Not in the text quoted here. The section ties flood load and flood resistant construction to the Florida Building Code, and its manufactured home and tank rules refer to elevations required by that code, such as Residential Section R322.2 for Zone A and R322.3 for Zone V.

Sources & Official References

Other rules in Jacksonville Beach

All Jacksonville Beach rules

Florida rules heatmap·Compare Jacksonville Beach to another location·View the Florida environmental rules overview

Get notified when Flood Elevation Requirements in Jacksonville Beach, FL changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Flood Elevation Requirements in Nearby Cities

How other cities in this county handle flood elevation requirements.

Jacksonville, FL
Some Restrictions