Key Facts

Governing section
City Code § 177-11, Local Design Flood Elevation
Standard freeboard
Base flood elevation plus 2 feet
AO Zone floor
3 feet above highest adjacent grade if unmapped
Critical facilities
500-year flood elevation plus 2 ft, ASCE 24
Enforcing official
City Engineer as Floodplain Administrator, § 177-12
Penalty
Up to $1,250 fine or 90 days, § 177-6

Summary

Long Branch sets its own local design flood elevation two feet above the state and FEMA base flood elevation in every mapped flood hazard area, with a three-foot-above-grade floor in AO zones, enforced by the City Engineer acting as Floodplain Administrator under Chapter 177 in Monmouth County, New Jersey.

§ 177-11. Establishing the local design flood elevation (LDFE). The local design flood elevation (LDFE) is established in the flood hazard areas determined in § 177-10, above, using the best available flood hazard data sources, and the Flood Hazard Area Control Act minimum statewide elevation requirements for lowest floors in A, Coastal A, and V Zones, ASCE 24 requirements for critical facilities as specified by the building code, plus additional freeboard as specified by this chapter. At a minimum, the local design flood elevation shall be as follows: A. For a delineated watercourse, the elevation associated with the best available flood hazard data area determined in § 177-10, above plus two feet or as described by N.J.A.C. 7:13 of freeboard; or

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: rev 4904719; v48 updated 2026-06-10; through 06-10-2026).

Full Breakdown

Chapter 177, Flood Damage Prevention, requires new construction and substantial improvements in a mapped flood hazard area to be built above the local design flood elevation (LDFE) Long Branch defines in § 177-11, not merely the FEMA or state base flood elevation. C. 7:13 and, for critical facilities, ASCE 24. C. 7:13, again plus freeboard. In an AO Zone shown on the FIRM, the LDFE is the highest adjacent grade plus the mapped depth number plus two feet of freeboard, or three feet above grade if no depth number is shown.

2%-annual-chance (500-year) flood elevation or the flood hazard area design elevation plus two additional feet of freeboard under ASCE 24. The City Engineer, designated Floodplain Administrator under § 177-12, reviews every permit application against these elevations and coordinates with the Construction Official to apply the flood provisions of the Uniform Construction Code.

Violations & Fines

Developing in a flood hazard area without meeting the local design flood elevation, or without a permit, violates § 177-6 and is punishable by a fine of up to $1,250, up to 90 days' imprisonment, or up to 90 days of community service, with each additional day a separate offense after a 30-day cure period. A building lacking the required elevation certification is presumed to be in violation under § 177-49 until the owner produces it.

Frequently Asked Questions

How much freeboard does Long Branch require above the base flood elevation?
Under § 177-11, the local design flood elevation is the best available flood hazard elevation plus two feet of freeboard for a delineated watercourse, matching the New Jersey Flood Hazard Area Control Act's statewide minimum at N.J.A.C. 7:13. Critical facilities in coastal high-hazard areas need an additional two feet on top of the higher of the 500-year flood elevation or that design elevation.
What if my property is in an AO Zone with no mapped flood depth?
Section 177-11C sets the local design flood elevation for AO Zones at the highest adjacent grade plus the FIRM's mapped depth number plus two feet of freeboard; if the FIRM panel shows no depth number at all, the floor is three feet above the highest adjacent grade.
Who decides how the flood elevation rules apply to my permit?
The City Engineer serves as Floodplain Administrator under § 177-12 and reviews every permit application to confirm the proposed development meets the local design flood elevation, coordinating with the Construction Official to apply the flood provisions of New Jersey's Uniform Construction Code.

Sources & Official References

Other rules in Long Branch

All Long Branch rules

Compare Long Branch to another location·View the New Jersey environmental rules overview

Get notified when Flood Elevation Requirements in Long Branch, NJ changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.