Lynn, MA Environmental Rules: Flood Elevation Requirements (2026)
Key Facts
- Data trigger
- Subdivisions over 50 lots or 5 acres
- Who supplies data
- The project proponent
- Unmapped A Zones
- Building dept. uses best available data
- Variance insurance warning
- Up to $25 per $100 of coverage
- Section
- Zoning Ordinance § 10.A.11, adopted July 7, 2025
Summary
Lynn requires base flood elevation data for any subdivision or development in the Floodplain Overlay District larger than 50 lots or 5 acres, whichever is smaller. Section 10.A.11 of the Zoning Ordinance makes the proponent supply technical data pinpointing the base flood elevation for every developable parcel on the design plans.
11. BASE FLOOD ELEVATION DATA FOR SUBDIVISION PROPOSALS. When proposing subdivisions or other developments greater than 50 lots or 5 acres (whichever is less., the proponent must provide technical data to determine base flood elevations for each developable parcel shown on the design plans.
Official source re-checked September 8, 2026: the cited page had not changed since it was quoted.
Full Breakdown
11 uses whichever number is less, 50 lots or 5 acres, so a compact but dense subdivision can trigger the requirement before a sprawling but sparse one does. 10's broader review standard for all subdivision and development proposals in the district, which the city assesses to confirm the project minimizes flood damage, that public utilities and facilities are sited and built to minimize flood damage, and that adequate drainage is provided. 8 directs the building department to obtain, review and reasonably use base flood elevation and floodway data from any federal, state or other source as the criteria for elevating residential structures to or above base flood level, floodproofing or elevating nonresidential structures, and prohibiting floodway encroachments.
15 further obligates the city to notify FEMA, the NFIP State Coordinator, the Massachusetts Department of Conservation and Recreation and the NFIP Program Specialist within six months whenever the city acquires data that changes a mapped base flood elevation, submitting the supporting technical or scientific data with that notice.
Violations & Fines
A subdivision or development proposal that omits the required base flood elevation data cannot satisfy Section 10.A.10's review standard, and the Building Commissioner, enforcing under Section 11.A, may withhold approval. Section 10.A.16 separately warns that a variance to build below the base flood level can raise flood insurance premiums by as much as $25 per $100 of coverage, a notice the city must give the property owner in writing and keep with the variance record.
Frequently Asked Questions
When does Lynn require base flood elevation data for a subdivision?
What if FEMA hasn't mapped base flood elevations for my Lynn parcel?
How much can building below base flood elevation raise flood insurance costs in Lynn?
Sources & Official References
Other rules in Lynn
Compare Lynn to another location·View the Massachusetts environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.