Skip to main content
CityRuleLookup

Lynn, MA Environmental Rules: Stormwater Management (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Review trigger
5,000+ sq ft floor area or 10+ parking spaces
Review body
7-member Site Plan Review Committee
Stormwater factor
Section 11.E.5.e, listed review criterion
Flood-zone drainage
AO/AH zones need drainage paths around structures
Hearing process
G.L. c.40A §§9, 11 special-permit procedure

Summary

Any Lynn project big enough to trigger site plan review, generally 5,000 or more square feet of new floor area, or ten or more added parking spaces, must satisfy the Site Plan Review Committee that its stormwater management system is adequate. Section 11.E.5.e of the Zoning Ordinance names stormwater adequacy as a mandatory review factor.

2. Applicability. Site plan review shall be required for: a. The construction, reconstruction, expansion or extension of one or more buildings on a lot where the combined gross floor area of all structures on the lot equals or exceeds 5,000 square feet. ... 5. Review Criteria. In conducting its review, the Approval Authority shall consider the adequacy of the proposal with respect to the following factors: ... e. Adequacy of stormwater management systems.

View official code

Official source re-checked September 8, 2026: the cited page had not changed since it was quoted.

Full Breakdown

2 to construction or expansion totaling 5,000 or more square feet of combined gross floor area on a lot, to a renovation or change of use adding ten or more parking spaces or relocating the building or site entrance, to any new or replacement building with a drive-through, to residential construction reaching three or more units on one lot, and to ground-mounted solar energy systems. 3 assigns review to a seven-member Site Plan Review Committee drawing department heads or designees from Community Development, EDIC, the Housing Authority and Neighborhood Development, Inspectional Services, Planning, Public Works, and the Water and Sewer Commission.

5, that committee weighs 'the adequacy of stormwater management systems' as one of nine listed review factors, alongside protection of natural and historic site features, impacts to adjoining properties, safe pedestrian, bicycle and vehicular access, fire and utility access, parking and loading adequacy, and waste removal. 9 imposes a narrower, floodplain-specific drainage rule: within Zones AO and AH, adequate drainage paths must be provided around structures on slopes to guide floodwaters around and away from them. The committee may adopt and amend its own rules and regulations covering design standards, filing them with the City Clerk.

Violations & Fines

A project that cannot demonstrate adequate stormwater management under Section 11.E.5.e does not clear site plan review, and the Approval Authority may condition or deny approval on that basis; applications proceed under the special-permit notice and hearing procedures of G.L. c. 40A, §§ 9 and 11 per Section 11.E.4, including a fourteen-day posted notice at the site. In the AO and AH flood zones, failing to route drainage around a structure under Section 10.A.9 exposes the project to the Building Commissioner's zoning enforcement under Section 11.A.

Frequently Asked Questions

What triggers site plan review in Lynn?
Section 11.E.2 requires site plan review for construction or expansion reaching 5,000 or more square feet of combined gross floor area, additions of ten or more parking spaces, any new building with a drive-through, residential projects reaching three or more units on one lot, and ground-mounted solar energy systems.
Who decides if a Lynn project's stormwater plan is adequate?
The seven-member Site Plan Review Committee, made up of department heads or designees from Community Development, EDIC, the Housing Authority and Neighborhood Development, Inspectional Services, Planning, Public Works and the Water and Sewer Commission, weighs stormwater adequacy under Section 11.E.5.e of the Zoning Ordinance.
Are there separate drainage rules in Lynn's flood zones?
Yes. Section 10.A.9 of the Floodplain Overlay District requires adequate drainage paths around structures built on slopes within Zones AO and AH, guiding floodwaters around and away from the structure, on top of the general stormwater review under site plan review.

Sources & Official References

Other rules in Lynn

All Lynn rules

Compare Lynn to another location·View the Massachusetts environmental rules overview

Get notified when Stormwater Management in Lynn, MA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.