Lynn, MA Environmental Rules: Stormwater Management (2026)
Key Facts
- Review trigger
- 5,000+ sq ft floor area or 10+ parking spaces
- Review body
- 7-member Site Plan Review Committee
- Stormwater factor
- Section 11.E.5.e, listed review criterion
- Flood-zone drainage
- AO/AH zones need drainage paths around structures
- Hearing process
- G.L. c.40A §§9, 11 special-permit procedure
Summary
Any Lynn project big enough to trigger site plan review, generally 5,000 or more square feet of new floor area, or ten or more added parking spaces, must satisfy the Site Plan Review Committee that its stormwater management system is adequate. Section 11.E.5.e of the Zoning Ordinance names stormwater adequacy as a mandatory review factor.
2. Applicability. Site plan review shall be required for: a. The construction, reconstruction, expansion or extension of one or more buildings on a lot where the combined gross floor area of all structures on the lot equals or exceeds 5,000 square feet. ... 5. Review Criteria. In conducting its review, the Approval Authority shall consider the adequacy of the proposal with respect to the following factors: ... e. Adequacy of stormwater management systems.
Official source re-checked September 8, 2026: the cited page had not changed since it was quoted.
Full Breakdown
2 to construction or expansion totaling 5,000 or more square feet of combined gross floor area on a lot, to a renovation or change of use adding ten or more parking spaces or relocating the building or site entrance, to any new or replacement building with a drive-through, to residential construction reaching three or more units on one lot, and to ground-mounted solar energy systems. 3 assigns review to a seven-member Site Plan Review Committee drawing department heads or designees from Community Development, EDIC, the Housing Authority and Neighborhood Development, Inspectional Services, Planning, Public Works, and the Water and Sewer Commission.
5, that committee weighs 'the adequacy of stormwater management systems' as one of nine listed review factors, alongside protection of natural and historic site features, impacts to adjoining properties, safe pedestrian, bicycle and vehicular access, fire and utility access, parking and loading adequacy, and waste removal. 9 imposes a narrower, floodplain-specific drainage rule: within Zones AO and AH, adequate drainage paths must be provided around structures on slopes to guide floodwaters around and away from them. The committee may adopt and amend its own rules and regulations covering design standards, filing them with the City Clerk.
Violations & Fines
A project that cannot demonstrate adequate stormwater management under Section 11.E.5.e does not clear site plan review, and the Approval Authority may condition or deny approval on that basis; applications proceed under the special-permit notice and hearing procedures of G.L. c. 40A, §§ 9 and 11 per Section 11.E.4, including a fourteen-day posted notice at the site. In the AO and AH flood zones, failing to route drainage around a structure under Section 10.A.9 exposes the project to the Building Commissioner's zoning enforcement under Section 11.A.
Frequently Asked Questions
What triggers site plan review in Lynn?
Who decides if a Lynn project's stormwater plan is adequate?
Are there separate drainage rules in Lynn's flood zones?
Sources & Official References
Other rules in Lynn