Key Facts

Lowest floor
At or above the base flood elevation
Zones AH, AO, VO
Above highest adjacent grade by FIRM depth, or two feet
Nonresidential floodproofing
Watertight one foot above the base flood level
Certification
Registered engineer or surveyor, once construction starts
Floodplain administrator
The city engineer
Penalty
Misdemeanor under section 5-31.005c

Summary

In the City of Novato, Marin County, California, new construction and substantial improvement in a special flood hazard area must have the lowest floor, basement included, at or above the base flood elevation. Nonresidential buildings can floodproof instead, and an engineer or surveyor must certify the lowest floor elevation once construction starts.

3.Elevation and Floodproofing.(a)New construction and substantial improvement of any structure shall have the lowest floor, including basement, elevated to or above the base flood elevation. Nonresidential structures may meet the standards in section 5-31.008a, 3(c). Upon start of construction of the structure, the elevation of the lowest floor including basement shall be certified by a registered professional engineer or surveyor. Such certification shall be provided to the floodplain administrator in a form and manner prescribed by the administrator.(b)New construction and substantial improvement of any structure in Zone AH, AO or VO shall have the lowest floor, including basement, elevated above the highest adjacent grade at least as high as the depth number specified in feet on the FIRM, or at least two feet if no depth number is specified. ... (c)Nonresidential construction shall either be elevated in conformance with section 5-31.008a, 3(a) or (b) or together with attendant utility and sanitary facilities:(1)Be floodproofed so that structure is watertight with walls substantially impermeable to the passage of water one foot above the base flood level;

Full Breakdown

Section 5-31.008 of the Novato Municipal Code, part of the City of Novato's Flood Damage Prevention Requirements in section 5-31, sets the construction standards for every area of special flood hazard inside the city. Under subsection a.3.(a), new construction and substantial improvement of any structure must have the lowest floor, including a basement, elevated to or above the base flood elevation. When construction starts, a registered professional engineer or surveyor certifies the elevation of the lowest floor, and the certification goes to the floodplain administrator in the form the administrator prescribes. Section 5-31.006 names the city engineer as floodplain administrator.

Shallow-flooding zones use a different measure. In Zone AH, AO or VO, subsection a.3.(b) requires the lowest floor to sit above the highest adjacent grade at least as high as the depth number printed in feet on the FIRM, or at least two feet if the FIRM prints no depth number.

Nonresidential structures have a floodproofing option under subsection a.3.(c). The building and its attendant utility and sanitary facilities must be watertight, with walls substantially impermeable to the passage of water one foot above the base flood level, must have structural components that resist hydrostatic and hydrodynamic loads and buoyancy, and must carry a certification from a registered professional engineer or architect. Fully enclosed areas below the lowest floor need openings to equalize flood forces: a minimum of two openings with a total net area of not less than one square inch for every square foot of enclosed area, with the bottom of every opening no higher than one foot above grade, unless the design is certified by an engineer or architect.

Two definitions in section 5-31.007 set the reach of the rule. The base flood is the flood with a one percent chance of being equalled or exceeded in any given year. A substantial improvement is any repair, reconstruction or improvement costing 50 percent or more of the structure's market value. The hazard areas come from the Flood Insurance Study for the City of Novato, California, Marin County, dated April 3, 1984, or the most recent study, kept on file with the Engineering Division of the Department of Community Development. New and replacement manufactured homes must also be elevated so the lowest floor is at or above the base flood elevation.

Violations & Fines

A violation of section 5-31, including failure to meet any condition or safeguard set in connection with a permit, is a misdemeanor under section 5-31.005c, and the City of Novato can take any lawful action needed to prevent or remedy it. A structure without the elevation certificate or other required evidence of compliance is presumed to be in violation until the documentation is provided. The floodplain administrator takes action to remedy violations.

Frequently Asked Questions

What is the base flood elevation for a property in Novato?
The code prints no single number. Section 5-31.007 defines the base flood as the flood with a one percent chance of being equalled or exceeded in any given year, and section 5-31.005 ties the mapped hazard areas to the Flood Insurance Study for the City of Novato, dated April 3, 1984, or the most recent study. The floodplain administrator reviews each permit against that data.
Does Novato require an elevation certificate?
The code requires a registered professional engineer or surveyor to certify the elevation of the lowest floor, basement included, once construction of the structure starts. The certification goes to the floodplain administrator, who keeps it available for public inspection under section 5-31.006d. A structure without the certification is presumed to be in violation until the documentation is provided.
Can a commercial building skip elevation in Novato?
Under subsection a.3.(c), a nonresidential structure can be floodproofed instead of elevated. The structure and its attendant utility and sanitary facilities must be watertight with walls substantially impermeable to water one foot above the base flood level, must resist hydrostatic and hydrodynamic loads and buoyancy, and must be certified by a registered professional engineer or architect.
Can the City of Novato grant a variance to build below the flood elevation?
Section 5-31.010 allows variances, but only on a showing of good and sufficient cause, a determination of exceptional hardship, and no increased flood heights or added threats to public safety. None is issued in a designated floodway if flood levels would rise. A recipient gets written notice that flood insurance cost will match the added risk, and a Grant of Variance is recorded with the Marin County Recorder.

Sources & Official References

Other rules in Novato

All Novato rules

California rules heatmap·Compare Novato to another location·View the California environmental rules overview

Get notified when Flood Elevation Requirements in Novato, CA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Flood Elevation Requirements in Nearby Cities

How other cities in Marin County handle flood elevation requirements.

San Rafael, CA
Some Restrictions