FEMA flood zone rules in Novato, CA, also called floodplain regulations or special flood hazard area (SFHA) rules, determine flood insurance requirements and elevation standards for new construction.
Key Facts
- F1 overlay
- Primary floodway; boat docks only, with Use Permit
- F2 overlay
- Secondary floodway; levees and fill need Review Authority finding
- F3 overlay
- 100-year flood plain; engineering and hydraulic study
- F2 agreement parties
- Owner, City, Marin County Flood Control District, Water Conservation District
- F3 fences and walls
- Building Permit required
- F3 grading
- 200 cubic yard exemption does not apply
Summary
In the City of Novato, California, Municipal Code § 19.16.050 applies a Flood Hazard (F) overlay in three tiers. F1 primary floodway land is limited to boat docks with a Use Permit, F2 secondary floodway land restricts levees and fill, and F3 land in the 100-year flood plain needs an engineering and hydraulic study.
A.Purpose and Applicability. ... The F overlay zoning district is applied to areas within the City prone to flood hazard risks, combined with any primary zoning district as shown on the Zoning Map and by Section 19.04.020 (Zoning Districts Established). The intent is to protect people and property from flood hazard risks by appropriately regulating development and land uses within an F overlay district. ... 1.F1 District. The F1 overlay is applied to lands within a primary floodway, including water channels and adjacent flood plains. Allowable land uses shall be limited to boat docks, with Use Permit approval. ... 3.F3 District. The F3 overlay district is applied to land within a 100-year flood plain.a.Limitations on Use. Allowable uses include all those allowed by the primary zoning district.b.Study Required. In cases where structures, fences, levees, dikes or filling may increase the depth or velocity of flood on adjacent lands within the flood plain area, an engineering and hydraulic study shall be prepared, and development shall occur only in compliance with Chapter 5 of the Municipal Code.
Full Breakdown
The F overlay is combined with a primary zoning district on the Zoning Map. Its stated intent is to protect people and property from flood hazard risks by regulating development and land uses. A suffix on the F symbol tells you which tier applies, and any land use normally allowed in the primary district can proceed unless the tier limits it.
F1 covers lands within a primary floodway, including water channels and adjacent flood plains. Allowable land uses are limited to boat docks, with Use Permit approval. F2 covers a secondary floodway, the portion between the F1 limits and where flood inundation can occur at low depths and velocities. Levees, dikes or filling can be allowed only where the Review Authority determines the activity is necessary to permit development and will not reduce the ponding capacity of the affected area. An exception can apply to a specified encroachment area or percentage of each parcel's ponding capacity, with the rest held as a ponding area. Before work starts, the landowner, the City, the Marin County Flood Control District and the Water Conservation District must sign an agreement. Lands in any F1 district on the property are dedicated to the City of Novato, the Marin County Flood Control District and the Water Conservation District, the landowner builds drainage improvements, and a performance bond can be required. Full use of undesignated F2 land requires the ultimate flood control channel improvements through the parcel and downstream to the mouth of the primary floodway.
F3 covers land within a 100-year flood plain, and all uses of the primary district are allowed. Where structures, fences, levees, dikes or filling can increase flood depth or velocity on adjacent land, an engineering and hydraulic study is required and development proceeds only in compliance with Chapter 5 of the Municipal Code. A proposed use must not increase the existing risk of flood damage on other lands, and conditions of approval can require structural measures and financial guarantees. The City can allow development that raises flood depths or velocities only after approving a flood protection plan and a written agreement with affected owners.
Two other chapters tighten F3 sites. All fences and walls in the F3 overlay require a Building Permit under Section 19.20.040.A.2. The grading exemption in Section 19.20.050 for movements under 200 cubic yards does not apply in the F-3 Overlay District.
Violations & Fines
Work in an F overlay without the required Use Permit, study or agreement is a Zoning Ordinance violation. Under Section 19.59.040 it is unlawful and a public nuisance, punishable as a misdemeanor or infraction at the City's election. Section 19.59.040 also authorizes Stop Work Orders, Section 19.59.090 adds a daily civil penalty under the Code Enforcement Fee Schedule, and Section 19.59.090 makes violators liable for the costs and damages the City suffers. The Director's Notice of Violation sets the correction deadline.
Frequently Asked Questions
What can be built in the Novato F1 flood overlay?
When does Novato require a flood study for development?
Who signs the agreement for fill in a Novato F2 district?
Does a fence in the Novato flood plain need a permit?
Sources & Official References
Other rules in Novato
California rules heatmap·Compare Novato to another location·View the California environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.
Flood Zones in Nearby Cities
How other cities in Marin County handle flood zones.