Portsmouth, VA Environmental Rules: Flood Elevation Requirements (2026)
Key Facts
- Freeboard requirement
- BFE + 3.0 feet (design flood elevation)
- Residential floodproofing below DFE
- Not allowed
- VE/V/Coastal A zones
- Same 3-ft buffer, on pilings
- Certification required
- PE or architect (non-residential)
- Large subdivision trigger
- >50 lots or 5 acres
Summary
New or substantially improved homes in Portsmouth's mapped flood zones must have their lowest floor, including HVAC ductwork and any basement, elevated at least 3.0 feet above the base flood elevation under § 14.1-11(d)(1). The city calls this the design flood elevation, and residential floodproofing is not allowed as a substitute.
Residential construction. New construction or substantial improvement of any residential structure (including manufactured homes) in Zones A1-30, AE, AH and A with detailed base flood elevations shall have the lowest floor including HVAC, duct work, and basement, elevated to at least the design flood elevation which is the BFE plus 3.0 feet. No floodproofing below the design flood elevation (DFE) of residential construction is allowed.
Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 65).
Full Breakdown
1-11(d)(1). The lowest floor, including the basement and any HVAC or duct work, must sit at or above that DFE, and unlike commercial buildings, homes cannot substitute flood-proofing for elevation below the DFE; the section states flatly that no floodproofing below the design flood elevation of residential construction is allowed. 1-11(d)(2): they may be elevated to the same BFE-plus-three standard or flood-proofed watertight to that level instead, but a Virginia-registered professional engineer or architect must certify the design and the floodplain administrator keeps that certification on file.
Coastal properties face an even stricter version of the same three-foot buffer: buildings in the VE or V zones (coastal high hazard areas) and the Coastal A zone must have the lowest horizontal structural member elevated at least three feet above base flood level on pilings or columns, anchored to resist wind and water loads acting simultaneously. 1-11(f)(4)).
Violations & Fines
Building below the required design flood elevation, or flood-proofing a residence instead of elevating it, violates § 14.1-11 and the compliance mandate in § 14.1-3, exposing the owner to the class 1 misdemeanor penalty in § 14.1-4, plus possible denial of a certificate of occupancy and loss of eligibility for federally backed flood insurance on the structure.
Frequently Asked Questions
How much higher than base flood elevation must my house be built?
Can I flood-proof my house instead of raising it?
Are coastal properties held to a different standard?
Who verifies my home meets the elevation requirement?
Sources & Official References
Other rules in Portsmouth
Compare Portsmouth to another location·View the Virginia environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.