Portsmouth, VA Environmental Rules: Stormwater Management (2026)
Key Facts
- Permit required before
- any land-disturbing activity
- Administrator
- city engineer or designee
- Civil penalty
- up to $32,500 per day
- Misdemeanor penalty
- up to 12 months jail, $2,500-$32,500 fine
- Storm-pollution fine
- up to $1,000 or 30 days jail
- Program effective date
- January 28, 2025 (Ord. 2025-09)
Summary
Portsmouth requires a city-issued stormwater permit before any land-disturbing activity and bans dumping process water, oil, antifreeze or debris into the storm system. Violations carry civil penalties up to $32,500 per day and misdemeanor jail time, enforced by the city engineer as administrator.
(a)Prohibited acts:(1)It shall be unlawful for any person to put, or allow to be put, any process water, wastewater, filth, animal or vegetable matters, chips, shavings or any other substance in the stormwater system, or do any injury thereto, or in any manner pollute the stormwater system.(2)It shall be unlawful for any person to pour or discharge, or to permit to be poured or discharges, or to deposit, so that the same may be discharged, any petroleum, gasoline, oil waste, antifreeze, or other fluids from vehicles or motor vehicles or equipment into any stormwater system....(b)Penalty for violation: Unless otherwise specified, any person or entity who shall violate any of the provisions of this section, or any regulation promulgated pursuant to authority granted by this section, shall be guilty of a misdemeanor and shall be subject to a fine not exceeding $1,000.00 or up to 30 days imprisonment for each violation or by both fine and imprisonment.
Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 65).
Full Breakdown
Under Sec. 1-7(a), no person may engage in land-disturbing activity in Portsmouth until the city has issued a stormwater permit under the Virginia Erosion and Stormwater Management Program (VESMP), administered locally by the city engineer or a designee (Sec. 1-2, Sec. 1-3). A qualifying project must submit a stormwater pollution prevention plan (SWPPP) combining an approved erosion and sediment control plan, an approved stormwater management plan and a pollution prevention plan before land disturbance begins (Sec. 1-8(a)-(b)). Permanent stormwater facilities require a recorded maintenance instrument that runs with the land and post-construction inspections at least once every five years (Sec.
1-14(b), Sec. 1-15(e)). Separately, Sec. 1-21(a) makes it unlawful to put process water, wastewater, filth, chips or vegetable matter into the stormwater system, or to pour petroleum, gasoline, oil waste or antifreeze into it, or to block a gutter, ditch or storm drain. If the administrator finds a permit violation or unauthorized discharge, the city can serve notices to comply, issue a stop-work order, or revoke the permit outright; a revoked permit means the owner must re-apply and pay the fee schedule in effect at the time of revocation and pass a new site inspection before work resumes (Sec.
1-19(a)-(b)). Penalties reach a civil charge of up to $32,500 for each violation, with each day of noncompliance a separate offense, and courts may weigh the economic benefit the violator gained from noncompliance (Sec. 1-19(d)). Willful or negligent violations are a misdemeanor punishable by up to 12 months in jail, a fine between $2,500 and $32,500, or both (Sec. 1-19(e)). The narrower storm-system pollution offense in Sec. 1-21(b) carries its own misdemeanor fine up to $1,000 or 30 days in jail, plus liability for the city's cleanup costs; police officers and fire marshals, not just the administrator, are authorized to enforce it (Sec. 1-21(d)). Applicants also owe land disturbance permit, site plan review and site inspection fees set in the Engineering Department's fee schedule (Sec. 1-22). 15:27.
Violations & Fines
Noncompliance triggers stop-work orders and permit revocation (Sec. 11.1-19(a)-(b)), a civil penalty up to $32,500 per violation with each day counted separately (Sec. 11.1-19(d)), and a misdemeanor of up to 12 months in jail and a $2,500-$32,500 fine for willful or negligent violations (Sec. 11.1-19(e)). Dumping into the storm system is a separate misdemeanor: a fine up to $1,000 or 30 days in jail (Sec. 11.1-21(b)), plus liability for city cleanup costs.
Frequently Asked Questions
Do I need a permit before disturbing land near Portsmouth's storm system?
What happens if I dump oil or debris into a Portsmouth storm drain?
How much can Portsmouth fine me for a stormwater permit violation?
Who administers Portsmouth's stormwater program?
Sources & Official References
Other rules in Portsmouth
Compare Portsmouth to another location·View the Virginia environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.